December 15, 2026

68 proposals across 52 counties, mostly bridge work (27) and asphalt and concrete resurfacing (14). The biggest by scope are the westbound I-80 rebuild in Polk County with three bridge replacements, the US 59 rebuild through Avoca, a 163,000 SY concrete overlay of Ginkgo Avenue in Washington County, and the IA 1 rebuild through Mt Vernon. District 3 (Sioux City) has the most proposals, 16.

Proposals
68
Counties
52
Bid items
2,997
  • Bridge27
  • Resurfacing14
  • Reconstruction9
  • Pavement maintenance6
  • Sidewalk and ADA3
  • Safety and traffic3
  • Culvert and drainage2
  • Other2
  • Trail1
  • Grading1

Where the work is

Shade is the number of proposals in each county. Pick a business type to see only the proposals with work for it. Click a county to list its proposals below.

None1234+68 proposals

Business type · proposals

Every county with a proposal. Pick a business type to narrow the map, the list and the counts.

Who should be looking

Proposals with work for each business type, by Iowa DOT district (assigned by county). Click a cell to list those proposals.

District 1 (Ames)District 2 (Mason City)District 3 (Sioux City)District 4 (Atlantic)District 5 (Fairfield)District 6 (Cedar Rapids)All
Traffic control59
Ready-mix concrete53
Aggregate and base suppliers48
Earthwork47
Signing and pavement marking45
Erosion control39
Hauling35
Guardrail32
Rebar and structural steel24
Precast and pipe22
Asphalt / HMA22
Geosynthetics20
Concrete paving and cement13
Electrical9

Worth a look

Eight proposals that stand out by scope or by the range of trades they need.

107Major

NE-35/235 Interchange to W US 65 Interchange (WB); NE 38th St 1.6 mi E of NE I-35/235 Interchange; NE I-35/80/235 Interchange to W US 65 Interchange; NE 29th St 0.7 mi E of NE I-35/235 Interchange (WB); Fourmile Creek 1.4 mi E of NE I-35/235 Interchange (WB)

I-80 · Polk County · District 1 (Ames)

Westbound I-80 regrade and new PCC pavement from the I-35/235 interchange to the west US 65 interchange, with three prestressed beam bridge replacements, overhead signs and ITS.

  • Concrete paving and cement
  • Earthwork
  • Aggregate and base suppliers
  • Hauling
  • Asphalt / HMA
  • Rebar and structural steel
  • Ready-mix concrete
  • Precast and pipe
  • Traffic control
  • Guardrail
  • Signing and pavement marking
  • Electrical
  • Geosynthetics
  • Erosion control

Seven-project I-80 contract that combines mainline PCC paving, three prestressed beam bridge replacements, overhead signs and ITS, touching nearly every trade.

104Major

In Mt Vernon, from SCL to NCL

IA 1 · Mt Vernon · Linn County · District 6 (Cedar Rapids)

Rebuilds IA 1 through Mt Vernon, from the south to the north city limits, in 9.5 in. concrete with new subbase, storm and sanitary sewer, water main, driveways and sidewalks.

  • Concrete paving and cement
  • Aggregate and base suppliers
  • Earthwork
  • Hauling
  • Ready-mix concrete
  • Precast and pipe
  • Geosynthetics
  • Traffic control
  • Signing and pavement marking
  • Erosion control

Two-season concrete rebuild of IA 1 through Mt Vernon with storm and sanitary sewer, water main and about 6,300 SY of sidewalk.

109Major

In Avoca, Pershing St to S of Co Rd F66

US 59 · Avoca · Pottawattamie County · District 4 (Atlantic)

Grade and replace US 59 in Avoca from Pershing St to south of Co Rd F66 with new 9.5 in. PCC pavement, new lighting and signs.

  • Concrete paving and cement
  • Earthwork
  • Aggregate and base suppliers
  • Hauling
  • Geosynthetics
  • Traffic control
  • Electrical
  • Signing and pavement marking
  • Erosion control
  • Ready-mix concrete
  • Guardrail
  • Precast and pipe

Two-season staged PCC reconstruction of US 59 through Avoca with about 71,000 SY of paving, new lighting, signs and heavy traffic control.

019Large

On MAGNOLIA RD, Over Mosquito Creek, from 260TH E 1 mile

MAGNOLIA RD · Pottawattamie County · District 4 (Atlantic)

Replace the Magnolia Rd bridge over Mosquito Creek with a 184 ft by 62 ft prestressed concrete beam bridge and rebuild about one mile of road in 8-in PCC pavement.

  • Concrete paving and cement
  • Ready-mix concrete
  • Rebar and structural steel
  • Precast and pipe
  • Earthwork
  • Aggregate and base suppliers
  • Hauling
  • Traffic control
  • Guardrail
  • Signing and pavement marking
  • Erosion control
  • Geosynthetics

County bridge replacement with about one mile of new PCC pavement, 27 prestressed beams, I-80 ramp closures and BNSF railroad work: nearly every trade.

110Large

In the city of Davenport, On W Central Park Avenue, from Lincoln Ave to 275' west of

W Central Park Avenue · Davenport · Scott County · District 6 (Cedar Rapids)

Reconstruction of W Central Park Avenue in Davenport with about 22,000 SY of PCC pavement, new subdrain, storm and sanitary sewer work, sidewalks and traffic signals.

  • Concrete paving and cement
  • Aggregate and base suppliers
  • Earthwork
  • Hauling
  • Ready-mix concrete
  • Precast and pipe
  • Electrical
  • Signing and pavement marking
  • Geosynthetics
  • Traffic control
  • Erosion control

Urban reconstruction that combines PCC paving, base stone, storm and sanitary sewer, sidewalks and new traffic signals.

161Large

On Lenox Ave NE 0.4 miles to D38 and 210th St 0.5 mi W of IA 31; On 220th Street, from East City limits of Anthon E 6 miles to Safford Avenue; On L 27, from D 50 S 6 miles to D 54

D38, L27, Lenox Ave · Woodbury County · District 3 (Sioux City)

Cold in-place recycling and HMA resurfacing on about 12 miles of D38 and L27, plus HMA resurfacing on Lenox Ave and 210th St.

  • Asphalt / HMA
  • Hauling
  • Aggregate and base suppliers
  • Traffic control
  • Signing and pavement marking
  • Guardrail
  • Ready-mix concrete
  • Precast and pipe
  • Electrical
  • Earthwork

About 150,000 SY of cold in-place recycling and about 32,000 TON of HMA on two 6-mile county roads, with shoulders, drainage and flagging.

158Large

Missouri State Line to IA 2

US 169 · Ringgold County · District 4 (Atlantic)

Mill, widen and resurface US 169 from the Missouri state line to IA 2 with an HMA intermediate course and a high performance thin lift surface.

  • Asphalt / HMA
  • Aggregate and base suppliers
  • Hauling
  • Earthwork
  • Electrical
  • Signing and pavement marking
  • Traffic control
  • Erosion control

About 49,000 TON of HMA and 18,000 TON of shoulder material on US 169, with widening, patching and lighting work.

114Large

On Ginkgo Ave, from 170th Street N to Wellman; On Ginkgo Avenue, from IA 92 N to past 170th Street intersection

Ginkgo Ave · Washington County · District 5 (Fairfield)

PCC overlay of Ginkgo Ave from IA 92 north to Wellman, about 163,000 SY placed over a pavement interlayer geotextile, with new granular shoulders and rumble strips.

  • Concrete paving and cement
  • Geosynthetics
  • Aggregate and base suppliers
  • Hauling
  • Signing and pavement marking
  • Asphalt / HMA

About 163,000 SY of PCC overlay over interlayer geotextile on a county road, with about 12,000 TON of shoulder stone.

All proposals

Each line is written from the proposal's schedule of items and its Description of Work. Open a line for key items, trades and timing.

68 of 68
001On 16 AVE, Over SPRING CK, S30 T86 R11Replacement of the 16th Avenue crossing of Spring Creek with a twin 10 ft by 8 ft by 46 ft reinforced box culvert.Benton · District 6 (Cedar Rapids)Culvert and drainageSmall30 items

Benton County is the contracting authority. Work removes the existing bridge and builds a twin cell cast-in-place box culvert, with channel excavation, a temporary stream diversion, Class E revetment over engineering fabric, and granular surfacing on the road. Two safety closures are listed. Winter work is required: the November 15 to April 1 free time does not apply.

16TH AVE. · Benton County · State ID BROS-C006(126)--8J-06

Key items

Structural concrete (RCB culvert)about 170CY
Reinforcing steelabout 25,000LB
Excavation, Class 10, roadway and borrowabout 1,200CY
Excavation, Class 10, wasteabout 1,000CY
Revetment, Class Eabout 470TON
Engineering fabric650SY

Who should look

  • Ready-mix concreteAbout 170 CY of structural concrete for the twin box culvert.
  • Rebar and structural steelAbout 25,000 LB of reinforcing steel for the box.
  • EarthworkClass 10 roadway, waste and channel excavation, about 2,900 CY combined, plus 750 CY of Class 20 excavation.
  • Aggregate and base suppliersAbout 470 TON of Class E revetment, about 130 TON of Class A crushed stone surfacing and 80 TON of special backfill.
  • HaulingAbout 1,000 CY of waste excavation and the revetment stone to move.
  • Geosynthetics650 SY of engineering fabric under the revetment.
  • Erosion controlSilt fence, sediment control devices, mulching and seeding.
  • Traffic controlTwo safety closures.

Timing

40 working days. Late start date September 13, 2027. Winter work is required: the November 15 to April 1 free time does not apply.

002In the city of Manning, On E ST, Over Willow CreekReplace the E St bridge over Willow Creek in Manning with a 90 ft by 30 ft continuous concrete slab bridge on steel H piles.Carroll · District 3 (Sioux City)BridgeMedium53 items

The City of Manning is the contracting authority. Work includes removal of the existing bridge, about 200 CY of structural concrete, aesthetic concrete barrier railing and steel pedestrian hand railing, and Class E revetment with grout in the channel. Approach work covers 8-in PCC pavement, bridge approach slabs, storm sewer with intakes and a manhole, sidewalk with detectable warnings, and a concrete driveway. Winter free time is not allowed; work continues on all working days.

E ST · Manning · Carroll County · State ID BROS-4702(609)--8J-14

Key items

Structural concrete (bridge)about 200CY
Reinforcing steel, epoxy coatedabout 52,000LB
Steel piles, HP 10 x 42about 1,400LF
Revetment, Class Eabout 850TON
Excavation, Class 10, channelabout 1,300CY
PCC pavement, Class C, 8 in.about 620SY

Who should look

  • Ready-mix concreteAbout 200 CY of bridge structural concrete plus aesthetic barrier railing, pile encasement, sidewalk and a concrete driveway.
  • Rebar and structural steelAbout 52,000 LB of epoxy-coated rebar, about 1,400 LF of HP 10 x 42 steel piles and steel pedestrian hand railing.
  • Aggregate and base suppliersAbout 850 tons of Class E revetment and 124 CY of modified subbase.
  • EarthworkAbout 1,300 CY of channel excavation plus roadway excavation, embankment and topsoil work.
  • Concrete paving and cementAbout 620 SY of 8-in Class C PCC pavement and about 400 SY of bridge approach.
  • Precast and pipeReinforced concrete storm sewer pipe from 15 to 24 in., three intakes, a 60-in manhole and a concrete apron.
  • HaulingRevetment stone and channel and roadway excavation to move on and off site.
  • Erosion controlSilt fence, sediment control devices, bonded fiber matrix mulch and seeding.
  • Traffic controlSchedule has safety closures beyond the lump sum traffic control.

Timing

90 working days. Late start date June 21, 2027. Winter free time (Nov 15 to Apr 1) is not allowed.

003In the city of Lowden, On Y 14 - Hoover Hwy, Over YANKEE RUN CREEKReplace the bridge on Y14 (Hoover Hwy) over Yankee Run Creek in Lowden with a 140 ft by 30 ft-6 in. continuous concrete slab bridge.Cedar · District 6 (Cedar Rapids)BridgeMedium41 items

The existing bridge is removed and replaced with a 140 ft continuous concrete slab bridge on a 15 degree skew, set on steel H piles with concrete encasement. Work includes roadway and channel excavation, Class C concrete approach pavement, Class E revetment and erosion stone over engineering fabric, and steel beam guardrail with end terminals. Cedar County is the contracting authority, and winter work is required on all working days.

Y14 · Lowden · Cedar County · State ID BRS-4555(606)--60-16

Key items

Structural concrete (bridge)about 360CY
Reinforcing steel, epoxy coatedabout 96,000LB
Steel piles, HP 10 x 42about 2,200LF
Revetment, Class Eabout 2,100TON
Excavation, Class 10, channelabout 3,200CY
PCC pavement, Class C, 10 in.about 860SY

Who should look

  • Ready-mix concreteAbout 360 CY of bridge structural concrete plus concrete approach slabs and about 860 SY of 10 in. concrete pavement.
  • Rebar and structural steelAbout 96,000 LB of epoxy coated reinforcing steel and about 2,200 LF of HP 10 x 42 steel piles.
  • Aggregate and base suppliersAbout 2,100 TON of Class E revetment, 495 TON of erosion stone, 271 CY of modified subbase and granular shoulders.
  • EarthworkAbout 2,400 CY of roadway and borrow excavation and about 3,200 CY of channel excavation.
  • HaulingOver 5,000 CY of excavation and over 2,500 TON of revetment and erosion stone to move.
  • GuardrailSteel beam guardrail with four barrier transition sections, four end anchors and four tangent end terminals.
  • GeosyntheticsAbout 390 SY of engineering fabric under the revetment.
  • Erosion controlSilt basins, about 840 LF of perimeter sediment control devices, mulching and seeding.
  • Traffic controlFour safety closures.

Timing

75 working days. Late start date June 1, 2027. Winter work required.

004Ideal Creek 1.2 mi W of Co Rd S56 in Mason CityDeck repair and a new concrete overlay on the IA 122 bridge over Ideal Creek in Mason City, with guardrail and approach work.Cerro Gordo · District 2 (Mason City)BridgeSmall24 items

The bridge is a 42'-6 x 68'-0 prestressed double-tee beam bridge. Work removes the existing overlay, repairs the deck and places a new overlay, bid as alternates: Class O PCC, or Class HPC-O PCC with fiber reinforcement. Roadway items include detour pavement, temporary concrete barrier, a temporary traffic signal, crash cushions, guardrail end work and pavement markings.

IA 122 · Mason City · Cerro Gordo County · State ID BRF-122-1(026)--38-17

Key items

Deck overlay (Class O or Class HPC-O PCC, alternates)about 340SY
Deck repair, Class Aabout 87SY
Excavation, Class 13, wasteabout 870CY
Detour pavementabout 760SY
Temporary barrier rail, concreteabout 400LF
Special backfillabout 278TON

Who should look

  • Ready-mix concreteAbout 340 SY of PCC deck overlay plus about 87 SY of Class A deck repair.
  • Traffic controlAbout 400 LF of temporary concrete barrier, a temporary traffic signal and 4 temporary crash cushions.
  • GuardrailAbout 160 LF of guardrail removal, 25 LF of new steel beam guardrail, 2 barrier transitions and 2 tangent end terminals.
  • EarthworkAbout 870 CY of Class 13 waste excavation and earth shoulder construction.
  • Aggregate and base suppliersAbout 278 TON of special backfill.
  • Signing and pavement markingAbout 39 STA of painted markings and 8 STA of wet retroreflective removable tape.

Timing

40 working days. Late start date August 2, 2027.

005On M 36, Over WILLOW CREEK, S30 T95 R37Replacement of the M36 bridge over Willow Creek with a 120'-0 x 30'-0 continuous concrete slab bridge on steel H piles.Clay · District 3 (Sioux City)BridgeMedium36 items

Clay County project let by Iowa DOT on a farm-to-market road. Work removes the existing bridge and builds a 120'-0 x 30'-0 continuous concrete slab bridge on steel H piles with TL-4 concrete open railing, concrete bridge approaches and Class E revetment over engineering fabric. The road is closed with safety closures, and the job includes grading, granular shoulders, guardrail end work, seeding and silt fence.

M36 · Clay County · State ID BROS-C021(165)--5F-21

Key items

Structural concrete (bridge)about 300CY
Reinforcing steel, epoxy coatedabout 76,000LB
Steel H piles (HP 10 x 42 and HP 12 x 53)about 2,200LF
Revetment, Class Eabout 2,200TON
Engineering fabricabout 2,600SY
Embankment-in-placeabout 1,100CY

Who should look

  • Ready-mix concreteAbout 300 CY of bridge structural concrete, concrete railing and about 476 SY of bridge approach.
  • Rebar and structural steelAbout 76,000 LB of epoxy coated rebar and about 2,200 LF of steel H piles.
  • Aggregate and base suppliersAbout 2,200 TON of Class E revetment and about 375 TON of Type B granular shoulders.
  • EarthworkAbout 1,100 CY of embankment, about 1,125 CY of roadway and borrow excavation and channel excavation.
  • HaulingAbout 2,200 TON of revetment stone plus over 1,000 CY each of embankment and excavation.
  • GeosyntheticsAbout 2,600 SY of engineering fabric under the revetment.
  • GuardrailAbout 240 LF of guardrail removal, 4 barrier transitions, 4 bolted end anchors and 4 tangent end terminals.
  • Erosion controlSeeding and mulching, about 800 LF of silt fence and slope sediment control devices.
  • Traffic control2 safety closures.

Timing

80 working days. Late start date July 6, 2027.

007Skunk River 0.5 mi N of IA 16 (SB)Removes and replaces the concrete overlay on the southbound US 61 bridge over the Skunk River, with deck repair, steel painting, new approaches and guardrail.Des Moines · District 5 (Fairfield)BridgeMedium49 items

The bridge is a 685 ft by 44 ft continuous welded girder bridge (Design 0126). The deck overlay is bid as two alternates: Class O PCC, or Class HPC-O PCC with fiber reinforcement and a trial batch. Paved shoulders are also bid as alternates, 8 in. PCC or 9 in. HMA with fog seal. The work also includes containment and painting of structural steel, a BR-203 bridge approach, grooving, temporary concrete barrier rail and a short detour pavement.

US 61 · Des Moines County · State ID BRF-061-2(132)--38-29

Key items

Deck overlay, Class O PCC or Class HPC-O PCC (alternates)about 3,300SY
Removal of existing P.C. overlayabout 3,300SY
Deck repair, Class Aabout 670SY
Bridge approach, BR-203about 720SY
Paved shoulder, 8 in. PCC or 9 in. HMA (alternates)about 900SY
Temporary barrier rail, concreteabout 2,200LF

Who should look

  • Ready-mix concreteAbout 3,300 SY of PCC deck overlay, about 670 SY of Class A deck repair and about 720 SY of BR-203 bridge approach.
  • GuardrailAbout 400 LF of steel beam guardrail with three barrier transitions, three end anchors and three tangent end terminals.
  • Traffic controlAbout 2,200 LF of temporary concrete barrier rail and two temporary crash cushions.
  • Signing and pavement markingAbout 130 STA of wet retroreflective removable tape, about 88 STA of painted markings and eight painted symbols.
  • Asphalt / HMAAlternate BB Option 2 bids about 900 SY of 9 in. HMA paved shoulder with fog seal.
  • Erosion controlAbout 1,200 LF of 20 in. perimeter sediment control device, about 310 LF of ditch checks, seeding and bonded fiber matrix mulch.

Timing

85 working days. Late start May 24, 2027. Winter free time not permitted.

008On 147TH ST, Over UNAMED CR, S26 T93 R07; On DOGWOOD RD, Over MINK CR, S9 T93N R07WReplace two existing bridges with twin cast-in-place reinforced concrete box culverts on 147th St and Dogwood Rd in Fayette County.Fayette · District 2 (Mason City)Culvert and drainageSmall17 items

Two sites: a twin 12 ft by 8 ft by 35 ft box culvert on 147th St over an unnamed creek, and a twin 12 ft by 10 ft by 35 ft box culvert on Dogwood Rd over Mink Creek. Each site removes the existing bridge and uses a temporary stream diversion. The Dogwood Rd site adds Class E revetment. Fayette County is the contracting authority.

147TH STREET, DOGWOOD ROAD · Fayette County · State ID HDP-C033(166)--71-33, HDP-C033(176)--71-33

Key items

Structural concrete (RCB culvert), both sitesabout 310CY
Reinforcing steel, epoxy coated, both sitesabout 52,000LB
Excavation, Class 20, both sitesabout 1,500CY
Revetment, Class E160TON

Who should look

  • Ready-mix concreteAbout 310 CY of structural concrete for two twin box culverts.
  • Rebar and structural steelAbout 52,000 LB of epoxy coated reinforcing steel.
  • EarthworkAbout 1,500 CY of Class 20 excavation across the two sites.
  • Aggregate and base suppliers160 TON of Class E revetment at the Dogwood Rd site.
  • Traffic controlEight safety closures, four at each site.

Timing

70 working days. Late start date July 19, 2027. Winter work required.

009On T 64, Over LITTLE CEDAR RIVER, S17 T96N R15WReplace the T64 bridge over the Little Cedar River with a 299 ft by 40 ft prestressed concrete beam bridge.Floyd · District 2 (Mason City)BridgeMedium59 items

Floyd County project. Removes the existing bridge and builds a 299 ft by 40 ft pretensioned prestressed concrete beam bridge on steel H-piles, with fiber-reinforced 4500 psi structural concrete, concrete open railing and about 490 SY of two-lane bridge approach. Roadwork includes embankment, channel excavation, HMA approach paving and base widening, Class E revetment and guardrail. The road cannot be closed until February 1, 2027.

T64 · Floyd County · State ID HDP-C034(114)--6B-34

Key items

Structural concrete 4500 psi or greater (fiber reinforced)about 480CY
Reinforcing steel, epoxy coatedabout 150,000LB
Prestressed concrete beams, BTC65 and BTC11515EACH
Steel piles, HP 10 x 57about 1,900LF
Embankment-in-placeabout 3,300CY
Revetment, Class Eabout 900TON

Who should look

  • Ready-mix concreteAbout 260 CY of bridge concrete plus about 480 CY of fiber-reinforced 4500 psi concrete, and bridge approach paving.
  • Rebar and structural steelAbout 150,000 LB of epoxy-coated rebar, about 28,000 LB of plain rebar, about 1,900 LF of HP 10 steel piles and structural steel.
  • Precast and pipe15 pretensioned prestressed concrete beams (BTC65 and BTC115) and 46 LF of 24 in. corrugated metal entrance pipe.
  • EarthworkAbout 3,300 CY of embankment, about 2,600 CY of roadway and borrow excavation and about 2,600 CY of channel excavation.
  • HaulingSeveral thousand CY of embankment and excavation, about 900 TON of revetment and about 930 TON of HMA.
  • Asphalt / HMAAbout 930 TON of high traffic HMA base, intermediate and surface courses, plus HMA base widening.
  • Aggregate and base suppliersAbout 900 TON of Class E revetment, 320 CY of modified subbase, 300 TON of Type B granular shoulders and erosion stone.
  • GuardrailSteel beam guardrail barrier transitions, end anchors and tangent end terminals, four each.
  • Geosynthetics2,000 SY of engineering fabric, billed with the revetment items.
  • Erosion controlAbout 1,900 LF of silt fence, ditch checks, sediment control devices, mulching and seeding.
  • Signing and pavement markingAbout 14 STA of painted pavement markings.
  • Traffic controlSchedule has safety closures beyond the lump sum traffic control.

Timing

120 working days. Late start date April 1, 2027. Road cannot be closed until February 1, 2027. No winter free time in winter 2027-2028.

010At the Co Rd C25 InterchangeConcrete deck overlay and repair on a 330-foot welded girder bridge at the Co Rd C25 interchange on I-35, with approach shoulder, guardrail and marking work.Franklin · District 2 (Mason City)BridgeSmall33 items

The bridge (Design No. 0127, 330'-0 x 32'-0 continuous welded girder) gets Class A deck repair, new steel extrusion joints and a PCC deck overlay with longitudinal grooving. The overlay is bid as alternates: Class O PCC, or Class HPC-O PCC with fiber reinforcement. Roadway items include HMA paved shoulder and surface course, shoulder strengthening, steel beam guardrail, temporary concrete barrier rail, temporary traffic signals and crash cushions. Winter free time is not allowed.

I-35 · Franklin County · State ID IMX-035-6(139)170--02-35

Key items

Deck overlay, Class O or Class HPC-O PCC (alternates)about 1,100SY
Longitudinal grooving, bridge deck and approachesabout 1,100SY
Temporary barrier rail, concreteabout 1,600LF
Shoulder strengthening, HMA or PCC, 8 in.about 630SY
Steel beam guardrailabout 220LF
Steel extrusion joint with neopreneabout 76LF

Who should look

  • Ready-mix concretePCC deck overlay of about 1,100 SY, deck repair and miscellaneous structural concrete.
  • Traffic controlAbout 1,600 LF of temporary concrete barrier rail, temporary traffic signals and 4 temporary crash cushions.
  • GuardrailAbout 220 LF of steel beam guardrail with barrier transitions and end terminals, after removal of the old rail.
  • Asphalt / HMAHMA surface course on about 530 SY after scarification and about 300 SY of 9-inch HMA paved shoulder.
  • Signing and pavement markingPainted markings and wet retroreflective removable tape for staging.
  • EarthworkAbout 370 CY of Class 13 excavation, plus embankment and special backfill at the approaches.
  • Rebar and structural steelAbout 1,200 LB of epoxy coated reinforcing steel.

Timing

45 working days. Late start date August 23, 2027. Winter free time not allowed.

011At the US 30 Interchange (SB); Allen Creek 1.9 mi N of US 30 (NB/SB)Deck replacement and repairs on three I-29 bridges near US 30, with new approaches, shoulders, guardrail and steel painting.Harrison · District 4 (Atlantic)BridgeLarge122 items

Two projects on I-29: a 219'-7 prestressed concrete beam bridge at the US 30 interchange (SB) and twin 155'-0 x 39'-0 continuous I-beam bridges over Allen Creek 1.9 mi north of US 30. The US 30 bridge and one Allen Creek bridge get new high performance concrete decks (about 580 CY total) with stainless and epoxy coated rebar, beam end repairs, new barrier rail and painting of structural steel with containment and asbestos removal. The second Allen Creek bridge gets Class A deck repair and a PCC overlay, bid as Class O or Class HPC-O alternates, plus Class E revetment and bank shaping at the creek. Roadway work includes PCC bridge approaches, PCC pavement and shoulders, detour pavement, guardrail, rumble strips and temporary concrete barrier rail.

I-29 · Harrison County · State ID IMX-029-4(138)76--02-43, IMX-029-5(266)78--02-43

Key items

Reinforcing steel, epoxy coated (incl. 80 ksi)about 217,000LB
High performance structural concreteabout 580CY
Bridge approach, BR-203about 1,300SY
Paved shoulder, P.C. concrete, 12 in.about 1,100SY
Temporary barrier rail, concreteabout 2,450LF
Revetment, Class E810TON

Who should look

  • Ready-mix concreteAbout 580 CY of high performance structural concrete for two new decks, about 770 LF of 3'-8 concrete barrier rail and a PCC deck overlay of about 695 SY.
  • Rebar and structural steelAbout 217,000 LB of epoxy coated rebar, about 9,300 LB of stainless steel rebar and about 2,000 LB of structural steel.
  • Concrete paving and cementAbout 760 SY of 9 in. and 12 in. Class C PCC pavement, about 1,300 SY of BR-203 bridge approaches and about 1,100 SY of 12 in. PCC paved shoulder.
  • GuardrailAbout 350 LF of new steel beam guardrail, 272 LF reset, with BA-201 transitions and BA-205 end terminals.
  • Traffic controlAbout 2,450 LF of temporary concrete barrier rail, 2 safety closures and 6 temporary crash cushions.
  • Aggregate and base suppliers810 TON of Class E revetment, about 1,100 TON of special backfill and about 315 CY of modified subbase.
  • EarthworkAbout 930 CY of Class 13 excavation for widening, 340 CY of channel excavation and 390 CY of embankment.
  • Signing and pavement markingPainted and multi-component liquid markings in cut grooves, symbols and legends, and wet retroreflective tape.
  • Asphalt / HMAAbout 390 SY of 9 in. HMA paved shoulder and about 1,970 SY of optional HMA or PCC shoulder strengthening.
  • Geosynthetics942 SY of engineering fabric under the Allen Creek revetment.
  • Erosion controlAbout 1,450 LF of perimeter and slope sediment control device and 25 LF of ditch checks.

Timing

complete by Nov 20, 2028. US 30 interchange project (138) due November 22, 2027. Allen Creek project (266) due November 20, 2028. Seeding and vegetation establishment: 20 working days, late start April 16, 2029.

012Iowa River 1.0 mi N of N Jct US 6; Iowa River Overflow 1.6 mi S of IA 220Deck overlays, joint replacement and beam end repairs on two US 151 prestressed concrete beam bridges over the Iowa River and the Iowa River Overflow.Iowa · District 6 (Cedar Rapids)BridgeMedium46 items

The two bridges are a 441'-0 x 44'-0 bridge over the Iowa River 1.0 mi N of N Jct US 6 and a 688'-6 x 44'-0 bridge over the Iowa River Overflow 1.6 mi S of IA 220. Each gets overlay removal, deck repair, a new overlay bid as alternates (Class O PCC, or Class HPC-O PCC with fiber reinforcement), steel extrusion joints, beam end repairs and painting of structural steel. Traffic runs behind 2,875 LF of temporary concrete barrier with temporary traffic signals and crash cushions.

US 151 · Iowa County · State ID BRF-151-1(36)--38-48, BRF-151-1(37)--38-48

Key items

Deck overlay (Class O or Class HPC-O PCC, alternates), both bridgesabout 5,400SY
Deck repair, Class Aabout 1,080SY
Steel extrusion joint with neopreneabout 365LF
Reinforcing steel, epoxy coatedabout 8,900LB
Temporary barrier rail, concrete2,875LF
Repair beam ends34EACH

Who should look

  • Ready-mix concreteAbout 5,400 SY of PCC deck overlay across the two bridges, about 1,080 SY of deck repair and about 66 CY of miscellaneous structural concrete.
  • Traffic control2,875 LF of temporary concrete barrier, 2 temporary traffic signals and 6 temporary crash cushions.
  • Rebar and structural steelAbout 8,900 LB of epoxy coated rebar and about 365 LF of steel extrusion joints.
  • Signing and pavement markingAbout 228 STA of painted pavement markings.
  • Guardrail4 guardrail blockout repairs.

Timing

90 working days. Late start date April 5, 2027.

013Iowa River 0.4 mi W of Co Rd W66Replaces the deck expansion joints on the IA 22 bridge over the Iowa River, 0.4 mile west of W66, with temporary signals and guardrail work.Johnson · District 6 (Cedar Rapids)BridgeSmall36 items

The bridge is a 441 ft by 40 ft pretensioned prestressed concrete beam bridge (Design 0727). Work includes about 82 LF of steel extrusion joint with neoprene, miscellaneous structural concrete and epoxy coated reinforcing steel. Traffic runs through temporary traffic signals and temporary concrete barrier rail, with detour pavement, guardrail replacement and multi-component liquid pavement markings.

IA 22 · Johnson County · State ID MB-022-5(500)46--77-52

Key items

Steel extrusion joint with neopreneabout 82LF
Structural concrete (miscellaneous)about 16CY
Reinforcing steel, epoxy coatedabout 1,400LB
Temporary barrier rail, concreteabout 1,100LF
Detour pavementabout 880SY
Excavation, Class 13, wasteabout 410CY

Who should look

  • Traffic controlOne set of temporary traffic signals, about 1,100 LF of temporary concrete barrier rail and four temporary crash cushions.
  • GuardrailAbout 150 LF of steel beam guardrail with four barrier transitions, eight end anchors and four tangent end terminals.
  • Signing and pavement markingAbout 93 STA of multi-component liquid markings in about 79 STA of cut grooves, plus painted and removable tape markings.
  • Ready-mix concreteAbout 16 CY of miscellaneous structural concrete for the joint replacement.
  • Rebar and structural steelAbout 1,400 LB of epoxy coated reinforcing steel.
  • EarthworkAbout 410 CY of Class 13 waste excavation, about 340 TON of special backfill and 50 CY of contractor furnished embankment.
  • Aggregate and base suppliersAbout 83 TON of Type B granular shoulders.
  • Erosion controlAbout 820 LF of silt fence and about 830 LF each of 12 in. and 20 in. perimeter sediment control device.

Timing

40 working days. Late start September 13, 2027. Winter free time not permitted.

014BNSF RR 0.1 mi E of W Jct US 65 in LucasDeck overlay, joint work and new concrete approaches on the US 34 bridge over the BNSF railroad in Lucas, with shoulder rebuilding and staged traffic control.Lucas · District 5 (Fairfield)BridgeMedium55 items

The bridge is a 210'-0 x 48'-0 continuous I-beam bridge over the BNSF railroad 0.1 mi E of W Jct US 65. Work removes the existing overlay, repairs the deck and places a new overlay bid as alternates (Class O PCC, or Class HPC-O PCC with fiber reinforcement), replaces joints and paving notches, paints structural steel and builds about 1,004 SY of BR-203 bridge approach. Roadway work adds HMA paved shoulder and shoulder strengthening, rumble strips, guardrail and markings, with temporary barrier, a temporary signal and flaggers. BNSF and Amtrak railroad right-of-way provisions apply.

US 34 · Lucas · Lucas County · State ID BRF-034-6(109)--38-59

Key items

Deck overlay (Class O or Class HPC-O PCC, alternates)about 1,120SY
Bridge approach, BR-2031,004SY
Shoulder strengthening, optional HMA or PCC, 8 in.about 880SY
Paved shoulder, HMA, 9 in.589SY
Temporary barrier rail, concrete1,550LF
Reinforcing steel, epoxy coated and stainlessabout 3,400LB

Who should look

  • Ready-mix concreteAbout 1,120 SY of PCC deck overlay, 1,004 SY of bridge approach, about 224 SY of deck repair and 23 CY of miscellaneous structural concrete.
  • Traffic control1,550 LF of temporary concrete barrier, a temporary traffic signal, 55 flaggers, 4 temporary crash cushions and a safety closure.
  • Asphalt / HMA589 SY of 9 in. HMA paved shoulder and about 880 SY of 8 in. shoulder strengthening bid as optional HMA or PCC.
  • Rebar and structural steelAbout 3,300 LB of epoxy coated rebar and 192 LB of stainless steel rebar.
  • Signing and pavement markingAbout 71 STA of painted markings, about 34 STA of wet retroreflective removable tape, grooves cut for markings and 3 multi-component symbols.
  • GuardrailAbout 262 LF of formed steel beam guardrail removed and reinstalled, 200 LF of removal and 4 tangent end terminals.
  • EarthworkAbout 455 CY of Class 13 waste excavation, 246 CY of special backfill and earth shoulder construction.
  • Erosion control2,160 LF of 20 in. perimeter and slope sediment control device.

Timing

70 working days. Late start date June 14, 2027.

015In the city of Grant, On 5TH ST, Over WEST NODAWAY RIVER, S3 T73 R36Replacement of the 5th Street bridge over the West Nodaway River in Grant with a 243-foot pretensioned prestressed concrete beam bridge on steel piling.Montgomery · District 4 (Atlantic)BridgeMedium41 items

City of Grant project let by Iowa DOT. Work removes the existing bridge and builds a 243'-0 x 24'-6 bridge on 12 C80 prestressed beams with HP 10 x 57 steel piles and TL-4 concrete open railing. It includes about 5,000 CY of channel excavation, about 1,700 TON of special revetment and crushed stone surfacing on the road. Winter free time is not allowed.

5TH ST · Grant · Montgomery County · State ID BROS-3052(602)--8J-69

Key items

Structural concrete (bridge)about 520CY
Reinforcing steelabout 107,000LB
Beams, pretensioned prestressed concrete, C8012EACH
Piles, steel, HP 10 x 57about 1,200LF
Revetment, specialabout 1,700TON
Excavation, Class 10 (roadway, waste and channel)about 10,000CY

Who should look

  • Ready-mix concreteAbout 520 CY of bridge structural concrete and TL-4 concrete open railing.
  • Rebar and structural steelAbout 107,000 LB of reinforcing steel, about 1,200 LF of HP 10 x 57 steel piling and about 3,300 LB of structural steel.
  • Precast and pipe12 C80 pretensioned prestressed concrete beams, plus a short 18-inch CMP entrance pipe.
  • Aggregate and base suppliersAbout 1,700 TON of special revetment and 300 TON of Class D crushed stone surfacing.
  • EarthworkAbout 3,500 CY of roadway excavation, 2,200 CY of waste excavation and 5,000 CY of channel excavation.
  • HaulingAbout 10,000 CY of Class 10 excavation and about 1,700 TON of revetment stone to move.
  • Erosion controlSilt fence, rock check dams, sediment control devices, and seeding and mulching on about 2 acres.
  • GuardrailAbout 50 LF of steel beam guardrail with barrier transitions and end terminals.
  • Traffic control2 safety closures.

Timing

120 working days. Late start date April 5, 2027. Winter free time not allowed.

016On Oriole Ave., Over MUD CREEK, S31 T95 R41Replace the Oriole Ave. bridge over Mud Creek with a 110 ft by 30.5 ft continuous concrete slab bridge on steel H piles.O'Brien · District 3 (Sioux City)BridgeSmall24 items

O'Brien County is the contracting authority. Work includes removal of the existing bridge, about 270 CY of structural concrete, TL-4 concrete open railing, two-lane bridge approaches and steel beam guardrail at the bridge ends. The channel gets Class E revetment over engineering fabric.

Oriole Ave. · O'Brien County · State ID BROS-C071(93)--5F-71

Key items

Structural concrete (bridge)about 270CY
Reinforcing steel, epoxy coatedabout 66,000LB
Steel piles, HP 10 x 57 and HP 10 x 421,700LF
Concrete open railing, TL-4about 240LF
Excavation, Class 20about 690CY
Revetment, Class Eabout 140TON

Who should look

  • Ready-mix concreteAbout 270 CY of bridge structural concrete, TL-4 concrete open railing and about 360 SY of bridge approach.
  • Rebar and structural steelAbout 66,000 LB of epoxy-coated rebar and 1,700 LF of HP 10 steel piles.
  • EarthworkAbout 690 CY of Class 20 excavation, about 400 CY of channel excavation and about 310 CY of embankment.
  • Guardrail50 LF of steel beam guardrail with 4 barrier transitions, 4 end anchors and 4 tangent end terminals.
  • Aggregate and base suppliersAbout 140 tons of Class E revetment.
  • Geosynthetics230 SY of engineering fabric under the revetment.
  • Erosion controlRural seeding and fertilizing on 0.42 acre.
  • Traffic controlSchedule has safety closures beyond the lump sum traffic control.

Timing

80 working days. Late start date June 28, 2027.

017Beaver Creek 0.5 mi N of Co Rd C16Deck repair and a 654 SY concrete deck overlay on the IA 12 bridge over Beaver Creek, a 130 ft by 44 ft continuous concrete slab bridge.Plymouth · District 3 (Sioux City)BridgeSmall22 items

Bidders choose one overlay alternate: Class O PCC, or Class HPC-O PCC with fiber reinforcement and a trial batch. Roadway work replaces about 800 SY of bridge approach, with special backfill, waste excavation, grooving, a bridge end drain and reinstalled guardrail. Traffic is staged with temporary concrete barrier rail, two temporary traffic signals, crash cushions and flaggers, plus about 2,300 SY of detour pavement.

IA 12 · Plymouth County · State ID BRF-012-2(042)--38-75

Key items

Deck overlay (Class O or Class HPC-O PCC)654SY
Bridge approach, BR-203about 800SY
Detour pavementabout 2,300SY
Special backfillabout 1,100TON
Temporary barrier rail, concrete1,000LF
Temporary traffic signals2EACH

Who should look

  • Ready-mix concrete654 SY of PCC deck overlay, about 65 SY of Class A deck repair and about 800 SY of bridge approach.
  • Traffic control1,000 LF of temporary concrete barrier rail, 2 temporary traffic signals, 4 temporary crash cushions and 20 flaggers.
  • EarthworkAbout 1,000 CY of Class 13 waste excavation and about 1,100 tons of special backfill.
  • Aggregate and base suppliersAbout 1,100 tons of special backfill behind the approaches.
  • HaulingAbout 1,000 CY of waste excavation out and about 1,100 tons of special backfill in.
  • Signing and pavement markingAbout 42 STA of painted markings, about 22 STA of wet retroreflective removable tape and marking removal.
  • GuardrailAbout 400 LF of formed steel beam guardrail removed and reinstalled.

Timing

55 working days. Late start date August 2, 2027.

018W Fork Floyd River 2.4 mi N of Co Rd R38Deck overlay, deck repair and steel painting on the US 75 bridge over the West Fork Floyd River, a 240 ft by 52 ft continuous I-beam bridge.Plymouth · District 3 (Sioux City)BridgeMedium35 items

Work removes the existing PC overlay, repairs the deck and places a new concrete overlay, bid as alternates: Class O PCC or Class HPC-O PCC with fiber reinforcement. It also replaces the steel extrusion joint, blast cleans and paints the structural steel under containment, and rebuilds the BR-204 bridge approaches. Traffic runs through the site on temporary concrete barrier rail and a temporary lane separator system, with crash cushions and temporary floodlighting. Winter work is required: the November 15 to April 1 free time does not apply.

US 75 · Plymouth County · State ID BRF-075-2(121)--38-75

Key items

Deck overlay (Class O PCC or Class HPC-O PCC, alternates)about 1,300SY
Removal of existing P.C. overlayabout 1,300SY
Bridge approach, BR-204about 840SY
Deck repair, Class A279SY
Temporary lane separator systemabout 3,800LF
Temporary barrier rail, concreteabout 1,000LF

Who should look

  • Ready-mix concreteAbout 1,300 SY of PCC deck overlay, 279 SY of Class A deck repair and about 840 SY of BR-204 bridge approach.
  • Traffic controlAbout 1,000 LF of temporary concrete barrier rail, about 3,800 LF of temporary lane separator, two temporary crash cushions and four floodlighting luminaires.
  • Guardrail410 LF of formed steel beam guardrail removed and reinstalled.
  • Signing and pavement markingPainted markings, wet retroreflective removable tape and grooves cut for markings.

Timing

70 working days. Late start date June 14, 2027. Winter work is required: the November 15 to April 1 free time does not apply.

019On MAGNOLIA RD, Over Mosquito Creek, from 260TH E 1 mileReplace the Magnolia Rd bridge over Mosquito Creek with a 184 ft by 62 ft prestressed concrete beam bridge and rebuild about one mile of road in 8-in PCC pavement.Pottawattamie · District 4 (Atlantic)BridgeLarge100 itemsWorth a look

Pottawattamie County is the contracting authority. The bridge uses 27 prestressed concrete beams (BTB40 and BTB100) on steel H piles, with about 1,000 CY of structural concrete, fiber reinforced concrete and stainless steel rebar. Roadway work covers about 11,000 SY of PCC pavement, PCC paved shoulders and driveways, granular shoulders, concrete culvert pipe including a trenchless crossing, subdrain, signs and a PCC railroad approach section. The contract has two 16-calendar-day closures of the I-80 westbound and eastbound ramps with incentive/disincentive, and requires BNSF railroad protective liability insurance.

MAGNOLIA RD · Pottawattamie County · State ID HDP-C078(210)--6B-78

Key items

PCC pavement, Class C, 8 in.about 11,000SY
Structural concrete (bridge)about 1,000CY
Prestressed concrete beams, BTB40 and BTB10027EACH
Reinforcing steel, plain, epoxy coated and stainlessabout 187,000LB
Steel piles, HP 14 x 73 and HP 10 x 574,680LF
Excavation, Class 10, roadway and borrowabout 8,700CY

Who should look

  • Concrete paving and cementAbout 11,000 SY of 8-in Class C PCC pavement, PCC paved shoulders and about 840 SY of bridge approach.
  • Ready-mix concreteAbout 1,000 CY of bridge structural concrete with about 410 CY fiber reinforced, barrier railing, about 1,400 SY of PCC driveways and sign footings.
  • Rebar and structural steelAbout 81,000 LB plain, about 103,000 LB epoxy-coated and about 3,100 LB stainless rebar, about 8,400 LB of structural steel and 4,680 LF of HP steel piles.
  • Precast and pipe27 prestressed concrete beams, plus concrete entrance and roadway culvert pipe from 15 to 36 in. with aprons and 173 LF of trenchless 24-in pipe.
  • EarthworkAbout 8,700 CY of roadway and borrow excavation, about 7,400 CY of embankment, 1,000 CY of unsuitable material and about 5,400 CY of topsoil.
  • Aggregate and base suppliersAbout 2,000 tons of Class E revetment, about 2,500 tons of Type A granular shoulders, about 2,200 CY of modified subbase and about 1,700 tons of crushed stone surfacing.
  • HaulingLarge earthwork volumes plus several thousand tons of revetment and granular material.
  • Traffic controlAbout 5,800 LF of temporary concrete barrier rail, 15 redirective crash cushions, 2 temporary traffic signals, 15 safety closures, 100 flaggers and portable message signs.
  • GuardrailSteel beam guardrail with transitions, end anchors and end terminals, guardrail removal and reinstall, and 170 LF of 72-in chain link fence.
  • Signing and pavement markingAbout 120 SF of Type A aluminum signs on steel tube posts, chevrons, and about 176 STA of painted markings with symbols.
  • Erosion controlAbout 4,900 LF of sediment control devices, 3,020 LF of silt fence ditch checks, mulching and seeding including native grass.
  • GeosyntheticsAbout 1,700 SY of engineering fabric.

Timing

215 working days. Late start date April 5, 2027. I-80 westbound and eastbound ramp closures limited to 16 calendar days each, with incentive/disincentive.

020On 240TH ST, Over WALNUT CREEK, S1 T81 R13Replacement of the 240th St bridge over Walnut Creek with a 188'-10 x 30'-6 prestressed concrete beam bridge on steel piles.Poweshiek · District 1 (Ames)BridgeMedium47 items

Poweshiek County project let by Iowa DOT on a local secondary road (S1 T81 R13). Work removes the existing bridge and builds a 188'-10 x 30'-6 bridge on 15 pretensioned prestressed concrete beams and steel H piles, with TL-4 concrete open railing and Class E revetment. About 8,800 CY of embankment and about 5,700 CY of channel excavation rebuild the approaches and channel, with crushed stone road surfacing, corrugated metal entrance pipes and new field fence. The road is closed with safety closures, and winter free time is not allowed.

240TH ST · Poweshiek County · State ID BROS-C079(74)--8J-79

Key items

Embankment-in-placeabout 8,800CY
Excavation, Class 10, channelabout 5,700CY
Granular surfacing on road, Class A crushed stoneabout 1,300TON
Structural concrete (bridge)about 270CY
Reinforcing steel, epoxy coatedabout 69,000LB
Beams, pretensioned prestressed concrete (B59 and B67)15EACH

Who should look

  • Ready-mix concreteAbout 270 CY of bridge structural concrete, 411 LF of TL-4 concrete open railing and concrete encasement of steel H piles.
  • Rebar and structural steelAbout 69,000 LB of epoxy coated rebar, 2,080 LF of steel H piles and about 3,100 LB of structural steel.
  • Precast and pipe15 pretensioned prestressed concrete beams plus 556 LF of corrugated metal entrance pipe from 18 to 60 in. with metal aprons.
  • EarthworkAbout 8,800 CY of embankment, about 5,700 CY of channel excavation and about 3,100 CY of roadway and borrow excavation.
  • Aggregate and base suppliersAbout 1,300 TON of Class A crushed stone road surfacing, about 1,000 TON of Class E revetment and 45 TON of driveway surfacing.
  • HaulingEmbankment and excavation in the thousands of CY plus about 2,300 TON of crushed stone and revetment.
  • Guardrail1,112 LF of field fence with 29 brace panels and removal of about 1,900 LF of barbed wire fence.
  • Erosion control3.3 acres of seeding and mulching, 990 LF of slope sediment control device and silt fence.
  • Traffic control4 safety closures.
  • Signing and pavement marking4 Type 3 object markers.

Timing

120 working days. Late start date April 19, 2027. Winter free time (Nov 15 to Apr 1) is not allowed.

021On 265TH ST, Over small stream, S29 T88N R36WReplacement of the 265th Street bridge over a small stream with a 40'-0 x 30'-0 single span concrete bridge on steel piles.Sac · District 3 (Sioux City)BridgeSmall23 items

Sac County project let by Iowa DOT on a local secondary road (S29 T88N R36W). Work removes the existing bridge and storm sewer pipe and builds a 40'-0 x 30'-0 single span concrete bridge on steel H piles with steel sheet piling, TL-4 concrete open railing, granular backfill and Class E revetment. About 1,803 CY of embankment rebuilds the approaches, and the road is closed with safety closures.

265TH STREET · Sac County · State ID BROS-C081(98)--8J-81

Key items

Embankment-in-place1,803CY
Structural concrete (bridge)about 113CY
Reinforcing steel, epoxy coatedabout 26,000LB
Piles, steel sheet4,488SF
Piles, steel, HP 10 x 421,050LF
Granular backfill356CY

Who should look

  • Ready-mix concreteAbout 113 CY of bridge structural concrete and 86 LF of concrete open railing.
  • Rebar and structural steelAbout 26,000 LB of epoxy coated rebar, 1,050 LF of steel H piles and 4,488 SF of steel sheet piling.
  • Earthwork1,803 CY of embankment, 356 CY of Class 20 excavation and 168 CY of channel excavation.
  • Aggregate and base suppliers356 CY of granular backfill and 70 TON of Class E revetment.
  • Hauling1,803 CY of embankment plus granular backfill and revetment stone.
  • Erosion controlHydraulic seeding and 100 LF of slope sediment control device.
  • Traffic control2 safety closures.
  • Signing and pavement marking4 Type 3 object markers.

Timing

65 working days. Late start date April 5, 2027. Winter work allowed in 2026/2027; no winter free time in 2027-2028.

022IMRL RR 0.4 mi E of US 61 (EB/WB)Deck replacement on the eastbound and westbound I-80 bridges over the IMRL railroad east of US 61, built in stages over two seasons.Scott · District 6 (Cedar Rapids)BridgeLarge87 items

Two 146'-8 pretensioned prestressed concrete beam bridges (Designs 0126 and 0226) get new high performance concrete decks, about 410 CY total, with epoxy coated and stainless steel rebar, new 3'-8 barrier rail, steel painting with containment and asbestos removal. The westbound bridge is staged in 2027 and the eastbound bridge in 2028, with about 18,500 SY of detour pavement and about 9,200 LF of temporary barrier rail; I-80 may not stay in a temporary lane configuration over winter. Roadway work includes bridge approaches, PCC shoulders, pipe culverts and slotted drains, cable guardrail replacement and about 6,600 TON of special backfill. Work over the railroad falls under the DS-23087 railroad right-of-way specification (CPKC).

I-80 · Scott County · State ID IMN-080-8(346)296--0E-82

Key items

Detour pavementabout 18,000SY
Reinforcing steel, epoxy coatedabout 133,000LB
High performance structural concreteabout 410CY
Temporary barrier rail, concrete9,275LF
Special backfillabout 6,600TON
Removal of pavementabout 23,000SY

Who should look

  • Ready-mix concreteAbout 410 CY of high performance structural concrete for two decks, about 700 LF of concrete barrier rail and about 1,200 SY of 8 in. PCC paved shoulder.
  • Rebar and structural steelAbout 133,000 LB of epoxy coated rebar and about 9,100 LB of stainless steel rebar.
  • Traffic control9,275 LF of temporary concrete barrier rail, 300 calendar days of portable dynamic message signs, temporary floodlighting, temporary rumble strip arrays and 7 crash cushions.
  • Aggregate and base suppliersAbout 6,600 TON of special backfill, 700 TON of Type A granular shoulders, about 370 CY of modified subbase and macadam stone wing armoring.
  • EarthworkAbout 3,900 CY of Class 13 waste excavation, 800 CY of roadway and borrow excavation and 460 CY of embankment.
  • HaulingAbout 6,600 TON of special backfill in and about 4,700 CY of excavation and 23,000 SY of pavement removal out.
  • Guardrail4,280 LF of cable guardrail removed, 800 LF of high tension cable guardrail and 184 line post foundations, plus about 520 LF of steel beam guardrail new or reset.
  • Precast and pipe440 LF of 18 in. roadway pipe culvert and 220 LF of 36 in. corrugated metal slotted drain.
  • Signing and pavement markingAbout 1,270 STA of painted pavement markings and 1,224 STA of marking removal.
  • Erosion control2,275 LF of silt fence with maintenance and removal, and topsoil.

Timing

200 working days. Overall: 200 working days, late start April 5, 2027. WB bridge (stages 2 and 3): 75 working days, late start May 10, 2027. EB bridge (stages 4 and 5): 75 working days, late start May 15, 2028. Working days suspended between the two bridges while all lanes are open.

023In the city of Davenport, On WISCONSIN AVE Over Duck CreekReplace the Wisconsin Ave bridge over Duck Creek in Davenport with a 138 ft by 28 ft prestressed concrete beam bridge with two 5 ft sidewalks.Scott · District 6 (Cedar Rapids)BridgeMedium69 items

City of Davenport project. Removes the existing bridge and builds a 138 ft 10 in. by 28 ft pretensioned prestressed concrete beam bridge with two 5 ft sidewalks, reinforced separation barrier and pedestrian hand railing, on steel H-piles. Approach work includes PCC pavement and bridge approach slabs, paved shoulders, subgrade stabilization with polymer grid, guardrail, chain link fence and Class E revetment. Traffic control includes two safety closures and a portable dynamic message sign.

WISCONSIN AVE · Davenport · Scott County · State ID BROS-1827(711)--8J-82

Key items

Structural concrete (bridge)about 400CY
Reinforcing steel, epoxy coatedabout 60,000LB
Prestressed concrete beams, A42 and A5018EACH
Steel piles, HP 12 x 53 and HP 10 x 57about 2,400LF
Revetment, Class E630TON
Bridge approach, BR-203about 370SY

Who should look

  • Ready-mix concreteAbout 400 CY of bridge concrete (about 200 CY fiber reinforced), about 370 SY of bridge approach, about 310 SY of 8 in. PCC pavement and PCC paved shoulders.
  • Rebar and structural steelAbout 60,000 LB of epoxy-coated rebar, about 15,000 LB of plain rebar, stainless rebar, about 2,400 LF of steel H-piles and about 4,200 LB of structural steel.
  • Precast and pipe18 pretensioned prestressed concrete beams (A42 and A50) and about 590 LF of 4 in. shoulder subdrain.
  • Aggregate and base suppliers630 TON of Class E revetment, 52 TON of erosion stone, about 110 CY of modified subbase, about 150 TON of granular shoulders and 66 CY of Class A crushed stone surfacing.
  • Earthwork1,250 CY of embankment, 800 CY of roadway and borrow excavation and 610 CY of topsoil work.
  • GuardrailSteel beam guardrail with BA-221 transitions and BA-225 end terminals, about 310 LF of reinforced separation barrier and about 300 LF of 48 in. chain link fence.
  • Geosynthetics512 SY of polymer grid subgrade stabilization and 923 SY of engineering fabric.
  • Erosion control1,788 LF of silt fence, wood excelsior ditch mat, bonded fiber matrix mulch and seeding.
  • Traffic controlTwo safety closures and 28 calendar days of a portable dynamic message sign.
  • Signing and pavement marking10 SF of Type A aluminum signs on perforated steel tube posts.

Timing

95 working days. Late start date June 14, 2027. No winter free time: work continues on all working days between November 15 and April 1.

024West Nishnabotna River 1.3 mi E of US 59Replace deck joints and paving notches on the IA 44 bridge over the West Nishnabotna River, 1.3 miles east of US 59.Shelby · District 4 (Atlantic)BridgeMedium39 items

Repairs to a 288 ft by 44 ft pretensioned prestressed concrete beam bridge: steel extrusion joints with neoprene glands, paving notch replacement and new bridge approach pavement. Traffic is carried with temporary traffic signals, temporary concrete barrier rail, crash cushions and detour pavement. Roadway work also replaces steel beam guardrail and puts down painted, multi-component liquid and wet retroreflective tape markings.

IA 44 · Shelby County · State ID MB-044-4(502)22--77-83

Key items

Steel extrusion joint with neoprene127LF
Paving notch replacementabout 120LF
Bridge approach pavement, as per planabout 940SY
Detour pavementabout 820SY
Temporary barrier rail, concreteabout 1,200LF
Temporary traffic signals1EACH

Who should look

  • Ready-mix concreteAbout 940 SY of bridge approach pavement and 32 CY of miscellaneous structural concrete for joint and notch repairs.
  • Traffic controlTemporary traffic signals, about 1,200 LF of temporary concrete barrier rail, four temporary crash cushions and two safety closures.
  • GuardrailAbout 300 LF of guardrail removed and 100 LF of steel beam guardrail placed with transitions, end anchors and end terminals.
  • Signing and pavement markingPainted and multi-component liquid markings, wet retroreflective removable tape, marking removal and grooves cut for markings.
  • Erosion controlAbout 1,200 LF of silt fence and about 1,300 LF of perimeter sediment control devices.
  • Earthwork250 CY of embankment and about 330 CY of Class 13 waste excavation.
  • Aggregate and base suppliersAbout 250 TON of special backfill and about 120 TON of Type B granular shoulders.
  • Rebar and structural steelAbout 2,200 LB of epoxy coated reinforcing steel.

Timing

75 working days. Late start date July 19, 2027. Winter work required.

025W Branch Indian Creek 0.5 mi E of Co Rd S14 (WB)Deck overlay, deck repair and steel painting on the westbound US 30 bridge over West Branch Indian Creek, a 190 ft by 30 ft continuous I-beam bridge.Story · District 1 (Ames)BridgeMedium41 items

Work removes the existing PC overlay, repairs the deck and places a new concrete overlay, bid as alternates: Class O PCC or Class HPC-O PCC with fiber reinforcement. It also paints the structural steel under containment, retrofits two bearing anchorages and repairs berm erosion. Roadway items replace guardrail at the bridge ends, add HMA paved shoulders and shoulder strengthening, bridge end drains and milled shoulder rumble strips, with temporary concrete barrier rail and crash cushions. Winter work is required: the November 15 to April 1 free time does not apply.

US 30 · Story County · State ID BRF-030-5(322)--38-85

Key items

Deck overlay (Class O PCC or Class HPC-O PCC, alternates)652SY
Removal of existing P.C. overlay652SY
Paved shoulder, hot mix asphalt mixture, 9 in.about 450SY
Steel beam guardrail325LF
Temporary barrier rail, concrete675LF
Modified subbaseabout 150CY

Who should look

  • Ready-mix concrete652 SY of PCC deck overlay, 130 SY of Class A deck repair and a PCC shoulder panel at the bridge end drain.
  • Guardrail325 LF of steel beam guardrail with barrier transitions, end anchors and tangent end terminals, replacing 476 LF removed.
  • Traffic control675 LF of temporary concrete barrier rail and two temporary crash cushions.
  • Asphalt / HMAAbout 450 SY of 9 in. HMA paved shoulder, plus about 300 SY of shoulder strengthening bid as HMA or PCC.
  • Signing and pavement markingPainted markings and symbols, about 160 STA of wet retroreflective removable tape.
  • Aggregate and base suppliersAbout 150 CY of modified subbase under the shoulders.
  • Erosion control550 LF of 20 in. perimeter and slope sediment control device.

Timing

55 working days. Late start date June 7, 2027. Winter work is required: the November 15 to April 1 free time does not apply.

02613th St 1.9 mi N of US 30 (NB/SB)Repair prestressed concrete beam ends on the northbound and southbound I-35 bridges at 13th St, 1.9 mi north of US 30.Story · District 1 (Ames)BridgeSmall10 items

Both bridges are 159 ft by 39 ft prestressed concrete beam bridges. Work covers beam repair as per plan, 17 beam end repairs and sealer coat on 19 beam ends. Traffic control includes portable dynamic message signs for 30 calendar days.

I-35 · Story County · State ID MBIN-035-1(510)114--0M-85

Key items

Repair beam ends17EACH
Sealer coat for prestressed concrete beam ends19EACH
Beam repair, as per planlump sumLS
Portable dynamic message sign30CDAY

Who should look

  • Ready-mix concreteConcrete repair of 17 prestressed beam ends plus lump sum beam repair on two bridges.
  • Traffic controlPortable dynamic message signs for 30 calendar days.

Timing

35 working days. Late start date June 7, 2027.

027Twelve Mile Creek 3.2 mi W of W Jct US 169Deck repair, an 836 SY concrete deck overlay and new bridge approaches on the US 34 bridge over Twelve Mile Creek, a 168 ft by 44 ft prestressed concrete beam bridge.Union · District 4 (Atlantic)BridgeMedium38 items

Bidders choose one overlay alternate: Class O PCC, or Class HPC-O PCC with fiber reinforcement and a trial batch. The contract also covers concrete and paving notch repair, about 740 SY of bridge approach, HMA paved shoulders and shoulder strengthening, new guardrail, and Class E revetment with bank shaping at the creek. Traffic is staged with temporary concrete barrier rail, a temporary traffic signal and crash cushions.

US 34 · Union County · State ID BRF-034-4(048)--38-88

Key items

Deck overlay (Class O or Class HPC-O PCC)about 830SY
Bridge approach, BR-203about 740SY
Shoulder strengthening, optional HMA or PCC, 8 in.about 1,500SY
Paved shoulder, HMA, 9 in.about 400SY
Revetment, Class Eabout 160TON
Temporary barrier rail, concreteabout 1,200LF

Who should look

  • Ready-mix concreteAbout 830 SY of PCC deck overlay, deck and concrete repair, paving notch replacement and about 740 SY of bridge approach.
  • Asphalt / HMAAbout 400 SY of 9-in HMA paved shoulder and about 1,500 SY of shoulder strengthening in HMA or PCC.
  • Guardrail150 LF of new steel beam guardrail with transitions, end anchors and end terminals, and 440 LF of guardrail removal.
  • Traffic controlAbout 1,200 LF of temporary concrete barrier rail, a temporary traffic signal and 4 temporary crash cushions.
  • EarthworkAbout 590 CY of Class 13 excavation, about 330 CY of special backfill and about 110 CY of channel excavation.
  • Aggregate and base suppliersAbout 160 tons of Class E revetment and erosion stone wing armoring.
  • GeosyntheticsAbout 300 SY of engineering fabric.
  • Signing and pavement markingAbout 81 STA of painted markings, about 25 STA of removable wet retroreflective tape and marking removal.
  • Erosion control900 LF of perimeter and slope sediment control device.

Timing

50 working days. Late start date August 30, 2027.

028On 20TH AVE, Over PAINTER CREEK, S20 T75 R25Replace the 20th Ave bridge over Painter Creek with a 145 ft by 24 ft prestressed concrete beam bridge.Warren · District 5 (Fairfield)BridgeMedium38 items

Warren County project on a local secondary road. Removes the existing bridge and builds a 145 ft by 24 ft pretensioned prestressed concrete beam bridge on HP 12 steel piles with concrete open railing. Channel work includes about 4,500 CY of channel excavation and about 1,700 TON of Class E revetment. Traffic control includes two safety closures.

20TH AVE · Warren County · State ID BROS-C091(144)--8J-91

Key items

Excavation, Class 10, channel4,500CY
Revetment, Class Eabout 1,700TON
Structural concrete (bridge)about 210CY
Reinforcing steelabout 52,000LB
Prestressed concrete beams, BTE1454EACH
Steel piles, HP 12 x 74800LF

Who should look

  • Ready-mix concreteAbout 210 CY of structural concrete for the bridge and about 350 LF of TL-4 concrete open railing.
  • Rebar and structural steelAbout 52,000 LB of reinforcing steel, 800 LF of HP 12 x 74 steel piles and about 2,700 LB of structural steel.
  • Precast and pipeFour BTE145 pretensioned prestressed concrete beams and 80 LF of 24 in. corrugated metal entrance pipe.
  • Aggregate and base suppliersAbout 1,700 TON of Class E revetment, 200 CY of revetment remove and replace, erosion stone wing armoring and 135 TON of Class D crushed stone surfacing.
  • Earthwork4,500 CY of channel excavation, about 2,100 CY of waste excavation and about 1,200 CY of roadway and borrow excavation.
  • HaulingAbout 7,800 CY of excavation including waste, plus about 1,700 TON of revetment stone.
  • Guardrail50 LF of steel beam guardrail with BA-221 transitions, end anchors and BA-225 end terminals.
  • Erosion controlSilt fence, 390 LF of sediment control devices, mulching and seeding.
  • Traffic controlSchedule has safety closures beyond the lump sum traffic control.

Timing

115 working days. Late start date July 6, 2027. Winter work allowed in 2026/2027 with no working days charged November 15, 2026 to April 1, 2027. No winter free time in winter 2027-2028.

029Reynolds Creek 1.6 mi W of Co Rd L37Replacement of the IA 175 bridge over Reynolds Creek, 1.6 mi west of Co Rd L37, with a 135'-0 x 44'-0 prestressed concrete beam bridge.Woodbury · District 3 (Sioux City)BridgeMedium53 items

Iowa DOT primary road project. Work removes the existing bridge and builds a 135'-0 x 44'-0 bridge (Design No. 0125) on six BTD135 prestressed concrete beams and steel H piles, with fiber reinforced structural concrete, stainless and epoxy coated rebar, and concrete barrier railing. Roadway work covers PCC bridge approaches, shoulders, steel beam guardrail with end terminals, three permanent crash cushions, and Class E revetment over engineering fabric. Traffic is handled with safety closures and a portable message sign, and a floating silt curtain is used in the creek.

IA 175 · Woodbury County · State ID BRF-175-2(009)--38-97

Key items

Structural concrete (bridge)about 290CY
Reinforcing steel, epoxy coatedabout 66,000LB
Reinforcing steel, stainless steelabout 3,000LB
Beams, pretensioned prestressed concrete, BTD1356EACH
Piles, steel, HP 10 x 571,870LF
Revetment, Class Eabout 1,000TON

Who should look

  • Ready-mix concreteAbout 290 CY of bridge structural concrete with fiber reinforcement, 324 LF of concrete barrier railing and about 750 SY of PCC bridge approach.
  • Rebar and structural steelAbout 66,000 LB of epoxy coated rebar, about 3,000 LB of stainless rebar, 1,870 LF of steel H piles and about 4,000 LB of structural steel.
  • Precast and pipe6 BTD135 pretensioned prestressed concrete beams.
  • Aggregate and base suppliersAbout 1,000 TON of Class E revetment, erosion stone wing armoring, modified subbase and Type B granular shoulders.
  • GeosyntheticsAbout 1,100 SY of engineering fabric under the revetment.
  • GuardrailSteel beam guardrail with a barrier transition, end anchor and tangent end terminal, plus 3 permanent crash cushions.
  • EarthworkAbout 670 CY of channel excavation, 150 CY of Class 20 excavation and minor roadway embankment and excavation.
  • Traffic control2 safety closures and 180 calendar days of portable dynamic message sign.
  • Erosion control200 LF of floating silt curtain, 635 LF of silt fence and 580 LF of slope sediment control device.
  • Signing and pavement marking6.93 STA of painted pavement markings with grooves cut, and 4 signs removed and reinstalled.
  • HaulingAbout 1,000 TON of revetment stone plus channel excavation.

Timing

100 working days. Late start date June 7, 2027. Winter free time (Nov 15 to Apr 1) is not allowed.

031At the Co Rd A38 InterchangeDeck repair and a PCC deck overlay on a 287'-0 x 32'-0 continuous welded girder bridge at the I-35 and Co Rd A38 interchange.Worth · District 2 (Mason City)BridgeSmall37 items

The bridge (Design No. 127) gets about 151 SY of Class A deck repair, a new steel extrusion joint with neoprene gland and a deck overlay of about 1,012 SY. Bidders choose one overlay alternate: Class O PCC, or Class HPC-O PCC with fiber reinforcement. Roadway work replaces guardrail at the ends, rebuilds shoulders with HMA and optional HMA or PCC shoulder strengthening, and regrooves the deck and approaches. Traffic runs through temporary concrete barrier rail and 2 temporary traffic signals.

I-35 · Worth County · State ID IMX-035-8(056)209--02-98

Key items

Deck overlay (Class O PCC or Class HPC-O PCC alternate)about 1,000SY
Deck repair, Class Aabout 150SY
Temporary barrier rail, concrete1,475LF
Reinforcing steel, epoxy coatedabout 1,800LB
Steel beam guardrail150LF
Temporary traffic signals2EACH

Who should look

  • Ready-mix concreteAbout 1,012 SY of PCC deck overlay, Class A deck repair and about 10 CY of miscellaneous structural concrete.
  • Traffic control1,475 LF of temporary concrete barrier rail, 2 temporary traffic signals and 4 temporary crash cushions.
  • GuardrailRemoval of about 310 LF of steel beam guardrail and 150 LF of new guardrail with 4 transition sections and 4 tangent end terminals.
  • Rebar and structural steelAbout 1,800 LB of epoxy coated reinforcing steel.
  • Asphalt / HMAAbout 364 SY of 9 in. HMA paved shoulder, about 576 SY of optional HMA or PCC shoulder strengthening and 29 TON of HMA surface course.
  • Aggregate and base suppliersAbout 332 TON of special backfill and 31 TON of Type B granular shoulders.
  • Signing and pavement markingPainted pavement markings and wet retroreflective removable tape.
  • EarthworkAbout 170 CY of Class 10 and Class 13 waste excavation.
  • Erosion control720 LF of perimeter and slope sediment control device.

Timing

45 working days. Late start date July 19, 2027. Winter free time (Nov 15 to Apr 1) not permitted.

101On 145th Avenue, from D22 North 4.6 Miles to 165th StreetA Portland cement concrete overlay on 4.6 miles of 145th Avenue from D22 north to 165th Street, over a pavement interlayer geotextile.Delaware · District 6 (Cedar Rapids)ResurfacingLarge26 items

Delaware County is the contracting authority on this farm-to-market road. Work places about 55,000 SY of PCC overlay on an interlayer geotextile, with new 8 in. and 10 in. PCC pavement sections, about 11,000 TON of Type B granular shoulders, modified subbase and crushed stone driveway surfacing. Bridge items add approach pavement, a steel extrusion joint and minor deck repair. The proposal lists 24 safety closures and flaggers. Winter work is required: the November 15 to April 1 free time does not apply.

145TH AVE · Delaware County · State ID FM-C028(110)--55-28

Key items

Portland cement concrete overlay, placement onlyabout 55,000SY
Portland cement concrete overlay, furnish onlyabout 11,000CY
Pavement interlayer geotextileabout 57,000SY
Granular shoulders, Type Babout 11,000TON
PCC pavement, Class C, 10 in.about 4,100SY
Modified subbaseabout 1,000CY

Who should look

  • Concrete paving and cementAbout 55,000 SY of PCC overlay (about 11,000 CY furnished), plus about 2,800 SY of 8 in. and about 4,100 SY of 10 in. PCC pavement.
  • Aggregate and base suppliersAbout 11,000 TON of Type B granular shoulders, about 1,400 TON of Class A crushed stone driveway surfacing and about 1,000 CY of modified subbase.
  • GeosyntheticsAbout 57,000 SY of pavement interlayer geotextile under the overlay.
  • HaulingAbout 11,000 TON of shoulder stone and about 1,100 CY of waste excavation to move.
  • Ready-mix concreteAbout 380 SY of bridge approach pavement, reinforced PCC driveways, miscellaneous structural concrete and deck repair.
  • EarthworkAbout 1,100 CY of Class 10 waste excavation.
  • Signing and pavement markingAbout 450 STA of painted pavement markings.
  • Traffic control24 safety closures and flaggers.

Timing

65 working days. Late start date June 21, 2027. Winter work is required: the November 15 to April 1 free time does not apply.

102In Guthrie Center (ADA – District 4)Replace sidewalk, curb and gutter and driveways with new concrete along IA 44 in Guthrie Center for ADA access.Guthrie · District 4 (Atlantic)Sidewalk and ADAMedium46 items

Crews remove about 2,600 SY of sidewalk and about 920 SY of paved driveway, then place 4 in. and 6 in. concrete sidewalk, detectable warnings, curb and gutter, concrete driveways, beam curb, concrete steps and a combined sidewalk and retaining wall. Utility work covers manhole and intake adjustments, 10 water service curb stops and 8 valve box replacements. Concrete work has an earlier completion date than final grading and seeding.

IA 44 · Guthrie Center · Guthrie County · State ID STPN-044-4(049)--2J-39

Key items

Sidewalk, P.C. concrete, 4 in.about 2,300SY
Sidewalk, P.C. concrete, 6 in.about 830SY
Driveway, P.C. concrete, 6 in.about 990SY
Curb and gutter, P.C. concrete, 2.5 ft.about 880LF
PC concrete beam curbabout 420LF
Detectable warningsabout 390SF

Who should look

  • Ready-mix concreteAbout 3,200 SY of concrete sidewalk, about 990 SY of concrete driveway, curb and gutter, beam curb, steps and a sidewalk retaining wall.
  • Erosion controlPerimeter sediment control devices, curb intake and grate intake sediment filters, excelsior mat, bonded fiber matrix mulch and urban seeding.
  • EarthworkAbout 470 CY of Class 10 and about 290 CY of Class 13 waste excavation.
  • Traffic controlSchedule has flaggers beyond the lump sum traffic control.

Timing

complete by Aug 30, 2027. Concrete work due August 10, 2027. Final grading, seeding and all other work due August 30, 2027.

103In the City of Monroe (ADA - District 1)Replaces sidewalks, curb ramps and driveways along IA 14 in Monroe for ADA, with concrete patching and minor drainage.Jasper · District 1 (Ames)Sidewalk and ADAMedium53 items

Work removes about 1,900 SY of sidewalk and about 2,000 SY of paved driveway and rebuilds them in 4, 6 and 8 in. PCC with detectable warnings. It also includes PCC steps, PCC beam curb, a combined sidewalk and retaining wall, curb and gutter, full-depth patches, 18 in. entrance pipe, sign replacement and sod. Concrete work has its own completion date ahead of final grading and seeding.

IA 14 · Monroe · Jasper County · State ID NHSN-014-4(071)--2R-50

Key items

Sidewalk, P.C. concrete, 4 in.about 1,800SY
Sidewalk, P.C. concrete, 6 in.about 640SY
Driveway, P.C. concrete, 6 in. and 8 in.about 2,200SY
Detectable warningsabout 600SF
Patches, full-depth finish, by areaabout 390SY
Surfacing, driveway500TON

Who should look

  • Ready-mix concreteAbout 2,500 SY of PCC sidewalk, about 2,200 SY of PCC driveway, about 370 LF of curb and gutter and about 390 SY of full-depth patches.
  • Erosion controlAbout 5,700 LF of 12 in. perimeter sediment control device, about 390 SQ of sod, and intake sediment filters.
  • Aggregate and base suppliers500 TON of driveway surfacing.
  • EarthworkAbout 490 CY of topsoil strip, salvage and spread and about 300 CY of Class 13 waste excavation.
  • Signing and pavement markingAbout 180 SF of Type A sheet aluminum signs, 54 LF of steel tube posts and 21 signs removed and reinstalled.
  • Precast and pipe58 LF of 18 in. entrance culvert pipe with six aprons.
  • Traffic controlSchedule has flaggers beyond the lump sum traffic control.

Timing

complete by Aug 30, 2027. Concrete work (Site 01) due August 10, 2027. Final grading and seeding (Site 00) due August 30, 2027.

104In Mt Vernon, from SCL to NCLRebuilds IA 1 through Mt Vernon, from the south to the north city limits, in 9.5 in. concrete with new subbase, storm and sanitary sewer, water main, driveways and sidewalks.Linn · District 6 (Cedar Rapids)ReconstructionMajor117 itemsWorth a look

The main project removes about 16,000 SY of pavement and places about 15,000 SY of 9.5 in. PCC pavement on modified subbase over polymer grid stabilization, with longitudinal subdrain. It also replaces storm sewer, intakes and manholes, sanitary sewer and about 1,300 LF of 8 in. water main installed trenchless, with valves and hydrants. A second project rebuilds about 6,000 SY of sidewalk. Work runs over two seasons in phases; IA 1 may not be detoured during winter (Nov 15 to April 1), and the contract includes Union Pacific Railroad requirements and concurrent Alliant Energy pole relocations.

IA 1 · Mt Vernon · Linn County · State ID NHSX-001-6(044)--3H-57, NHSN-001-6(045)--2R-57

Key items

Standard or slip form PCC pavement, Class C, 9.5 in.about 15,000SY
Modified subbaseabout 7,100CY
Excavation, Class 10, wasteabout 8,100CY
Subgrade stabilization material, polymer gridabout 4,800SY
Sidewalk, P.C. concrete, 4 in. and 6 in.about 6,300SY
Water main, trenchless, PVC, 8 in.about 1,300LF

Who should look

  • Concrete paving and cementAbout 15,000 SY of 9.5 in. Class C PCC mainline pavement.
  • Aggregate and base suppliersAbout 7,100 CY of modified subbase, about 1,400 TON of macadam stone base and about 1,200 TON of Class A crushed stone driveway surfacing.
  • EarthworkAbout 8,100 CY of Class 10 waste excavation, about 910 CY of roadway excavation and 850 CY of unsuitable material removal.
  • HaulingAbout 8,100 CY of waste excavation hauled out and about 7,100 CY of modified subbase hauled in.
  • Ready-mix concreteAbout 6,300 SY of PCC sidewalk, about 2,800 SY of PCC driveway, curb and gutter and full-depth patches.
  • Precast and pipeAbout 450 LF of 12 to 24 in. RCP storm sewer, storm and sanitary manholes, 12 intakes and about 8,600 LF of shoulder subdrain.
  • GeosyntheticsAbout 4,800 SY of polymer grid subgrade stabilization.
  • Traffic control56 calendar days of portable dynamic message signs and 41 safety closures.
  • Signing and pavement markingPreformed thermoplastic symbols and tape, about 52 STA of painted markings and grooves cut for markings.
  • Erosion controlAbout 970 LF of perimeter sediment control device, stabilized construction entrance, seeding and mulching.

Timing

250 working days. Late start June 1, 2027, 250 working days overall. Phases 5 and 6 in 100 working days from June 1, 2027; Phases 1, 2, 3 and 4C in 120 working days with late start April 3, 2028.

105On B14, from 480th Ave E 2 miles to 500th Ave and On N52, from B14 to Emmet CountyRemoval and replacement of county pavement on B14 and N52 with about 41,000 SY of 8-inch PCC on a new soil-fly ash/cement subbase.Palo Alto · District 3 (Sioux City)ReconstructionMedium25 items

Palo Alto County project let by Iowa DOT, on B14 from 480th Ave E 2 miles to 500th Ave and on N52 from B14 to Emmet County. The old pavement is removed and crushed, then about 52,000 SY of soil-fly ash/cement subbase and a modified subbase (place only) go under 8-inch Class C PCC. Grading includes contractor-furnished embankment and furnished topsoil. Traffic is handled with 4 safety closures and flaggers.

B14 · Palo Alto County · State ID STP-S-C074(118)--5E-74

Key items

PCC pavement, Class C, 8 in.about 41,000SY
Construction of soil-fly ash/cement subbaseabout 52,000SY
Removal and crushing of pavementabout 35,000SY
Modified subbase, place onlyabout 5,700CY
Embankment-in-place, contractor furnishedabout 5,600CY
Topsoil, furnish and spreadabout 5,800CY

Who should look

  • Concrete paving and cementAbout 41,000 SY of 8-inch PCC pavement and about 52,000 SY of soil-fly ash/cement subbase.
  • EarthworkAbout 5,600 CY of contractor-furnished embankment, 3,600 CY of roadway excavation and 5,800 CY of furnished topsoil.
  • HaulingAbout 5,600 CY of contractor-furnished embankment and 5,800 CY of topsoil to deliver.
  • Signing and pavement markingAbout 370 STA of painted pavement markings.
  • Erosion controlSeeding and mulching on about 10 acres, and sediment control devices.
  • Traffic control4 safety closures and 100 flagger days.

Timing

100 working days. Late start date May 31, 2027. Winter free time not allowed.

106Co Rd C80 and Co Rd C70 IntersectionsGrading and new PCC pavement at the US 75 intersections with Co Rd C80 and Co Rd C70, with new signs and lighting.Plymouth · District 3 (Sioux City)ReconstructionLarge83 items

Iowa DOT bid this as three projects: roadway, traffic signs and lighting. The roadway project removes about 12,000 SY of pavement and places about 7,600 SY of 10 in. PCC pavement and about 4,100 SY of PCC paved shoulders, with special backfill, polymer grid subgrade stabilization, shoulder subdrain, 24 in. concrete roadway pipe and milled rumble strips. The sign project replaces Type A and Type B signs on steel posts, and the lighting project adds 24 lighting poles with about 5,500 LF of electrical circuits and 2 control cabinets. Traffic is handled with safety closures, a permanent road closure and portable message signs.

US 75 · Plymouth County · State ID NHSN-075-2(137)--2R-75, NHSN-075-2(138)--2R-75, NHSN-075-2(139)--2R-75

Key items

PCC pavement, Class C, Class 3 durability, 10 in.about 7,600SY
Paved shoulder, P.C. concrete, 10 in.about 4,100SY
Removal of pavementabout 12,000SY
Special backfillabout 4,400CY
Lighting poles24EACH
Electrical circuitsabout 5,500LF

Who should look

  • Concrete paving and cementAbout 7,600 SY of 10 in. PCC pavement and about 4,100 SY of PCC paved shoulders at the two intersections.
  • Electrical24 lighting poles, about 5,500 LF of electrical circuits, 12 handholes and 2 control cabinets.
  • Signing and pavement markingAbout 850 SF of Type A and about 1,000 SF of Type B signs on steel posts, plus painted and preformed thermoplastic markings in cut grooves.
  • EarthworkAbout 4,400 CY of special backfill, about 1,800 CY of roadway and borrow excavation and about 1,100 CY of waste excavation.
  • HaulingSeveral thousand CY of backfill and excavation plus pavement removal.
  • Traffic control11 safety closures, a permanent rural road closure and 100 calendar days of portable dynamic message sign.
  • Precast and pipe278 LF of 24 in. concrete roadway pipe with concrete and safety slope aprons.
  • Geosynthetics526 SY of polymer grid subgrade stabilization and 47 SY of engineering fabric.
  • Aggregate and base suppliers194 TON of Type B granular shoulders and 26 TON of erosion stone.
  • Erosion controlAbout 2,700 LF of silt fence, 12 silt basins, sediment control devices and seeding with bonded fiber matrix mulch.
  • Ready-mix concrete69 LF of PCC curb and gutter, a PCC median and 6 concrete sign post footings.

Timing

135 working days. Late start date April 5, 2027. Winter free time (Nov 15 to Apr 1) is not allowed.

107NE-35/235 Interchange to W US 65 Interchange (WB); NE 38th St 1.6 mi E of NE I-35/235 Interchange; NE I-35/80/235 Interchange to W US 65 Interchange; NE 29th St 0.7 mi E of NE I-35/235 Interchange (WB); Fourmile Creek 1.4 mi E of NE I-35/235 Interchange (WB)Westbound I-80 regrade and new PCC pavement from the I-35/235 interchange to the west US 65 interchange, with three prestressed beam bridge replacements, overhead signs and ITS.Polk · District 1 (Ames)ReconstructionMajor290 itemsWorth a look

Seven projects on I-80 in Polk County. The paving project removes about 81,000 SY of pavement and builds 11.5 in. QM-C PCC pavement and 11.5 in. PCC paved shoulders on granular subbase and polymer grid, with about 11,000 TON of very high traffic HMA, new concrete barrier, storm sewer and subdrains. Three pretensioned prestressed concrete beam bridges are replaced on steel H piles: NE 38th St (292'-0 x 40'-0), NE 29th St (224'-0 x 77'-1, WB) and Fourmile Creek (219'-0 x 85'-4, WB), using about 148,000 LB of stainless clad rebar on NE 38th St and drilled shafts at Fourmile Creek. Other projects add two steel overhead sign trusses and a dynamic message sign on drilled shafts, ITS fiber, conduit and lighting, and about 1,600 TON of HMA on the NE 38th St pavement project. Traffic runs behind about 34,000 LF of temporary concrete barrier rail.

I-80 · Polk County · State ID IM-NHS-080-4(083)138--03-77, IM-080-4(084)138--13-77, IM-080-4(089)140--13-77, IM-080-4(090)140--13-77, ITS-080-4(102)138--25-77, IM-080-4(110)139--13-77, IM-080-4(111)139--13-77

Key items

Granular subbaseabout 68,000SY
Excavation, Class 10, wasteabout 42,000CY
Paved shoulder, P.C. concrete, 11.5 in.about 38,000SY
PCC pavement, QM-C, Class 3I durability, 11.5 in.about 24,000SY
Hot mix asphalt, intermediate and surface coursesabout 12,000TON
Beams, pretensioned prestressed concrete34EACH

Who should look

  • Concrete paving and cementAbout 24,000 SY of 11.5 in. QM-C PCC mainline pavement, about 38,000 SY of 11.5 in. PCC paved shoulder and about 1,790 SY of BR-203 bridge approaches.
  • EarthworkAbout 42,000 CY of Class 10 waste excavation, 11,600 CY of roadway and borrow excavation and about 9,000 CY of compaction with moisture control.
  • Aggregate and base suppliersAbout 68,000 SY of granular subbase, about 22,000 CY of special backfill, about 8,000 TON of erosion stone, about 1,500 TON of Class E revetment, about 2,100 TON of granular shoulders and about 1,200 CY of modified subbase.
  • HaulingAbout 54,000 CY of excavation, 22,000 CY of special backfill, 12,000 TON of HMA and 81,000 SY of pavement removal.
  • Asphalt / HMAAbout 11,000 TON of very high traffic HMA intermediate and surface course and about 1,600 TON of high traffic HMA at NE 38th St, plus HMA surface patches.
  • Rebar and structural steelAbout 148,000 LB of stainless clad rebar, about 300,000 LB of plain and epoxy coated rebar, about 5,300 LF of steel H piles and about 20,000 LB of structural steel.
  • Ready-mix concreteAbout 1,600 CY of bridge, 4500 psi and high performance structural concrete, barrier railing, 532 LF of drilled shafts and about 14,700 LF of BA-100 and BA-102 concrete barrier.
  • Precast and pipe34 pretensioned prestressed concrete beams, about 3,300 LF of RCP storm sewer, 68 barrier intakes and about 29,000 LF of subdrain.
  • Traffic controlAbout 34,000 LF of temporary concrete barrier rail, 17 safety closures, 275 calendar days of portable dynamic message signs and 14 temporary crash cushions.
  • GuardrailAbout 14,700 LF of BA-100 and BA-102 concrete barrier, 1,125 LF of steel beam guardrail, 1,000 LF of high tension cable guardrail and 428 LF of chain link fence.
  • Signing and pavement markingTwo steel overhead sign truss spans, a dynamic message sign installation, 780 SF of Type B signs and about 2,800 STA of painted, multi-component liquid and preformed tape markings, with about 1,200 STA of cut grooves.
  • ElectricalITS fiber optic cable, about 2,900 LF of HDPE and metallic conduit, copper wire, cabinets and handholes, 4 lighting poles and 804 LF of electrical circuits.
  • GeosyntheticsAbout 46,000 SY of polymer grid subgrade stabilization and about 15,000 SY of engineering fabric.
  • Erosion controlAbout 15,000 LF of silt fence and silt fence ditch checks, silt basins, seeding, mulching and wood excelsior mat.

Timing

complete by Dec 31, 2027. Single completion date for the whole proposal.

109In Avoca, Pershing St to S of Co Rd F66Grade and replace US 59 in Avoca from Pershing St to south of Co Rd F66 with new 9.5 in. PCC pavement, new lighting and signs.Pottawattamie · District 4 (Atlantic)ReconstructionMajor109 itemsWorth a look

Iowa DOT removes about 63,000 SY of pavement and places about 71,000 SY of 9.5 in. QM-C PCC pavement and about 15,000 SY of PCC paved shoulders over polymer grid subgrade stabilization and modified subbase, with about 16,000 LF of new shoulder subdrain. Work is staged over two construction seasons with detour pavement, temporary traffic signals, temporary barrier rail, flaggers and pilot cars, and no work in winter conditions during Stage 3. A separate lighting project replaces 22 light poles with about 8,600 LF of electrical circuits, and the sign work replaces Type A and Type B signs. A utility bid attachment is part of the proposal.

US 59 · Avoca · Pottawattamie County · State ID NHSX-059-3(056)--3H-78, NHSX-059-3(064)--3H-78

Key items

PCC pavement, QM-C, Class 3 durability, 9.5 in.about 71,000SY
Subgrade stabilization material, polymer gridabout 78,000SY
Excavation, Class 10, roadway and borrowabout 26,000CY
Special backfillabout 17,000CY
Modified subbaseabout 15,000CY
Paved shoulder, P.C. concrete, 9.5 in.about 15,000SY

Who should look

  • Concrete paving and cementAbout 71,000 SY of 9.5 in. QM-C PCC pavement and about 15,000 SY of PCC paved shoulders.
  • EarthworkAbout 26,000 CY of roadway and borrow excavation, about 17,000 CY of special backfill and about 13,000 CY of contractor furnished embankment.
  • Aggregate and base suppliersAbout 15,000 CY of modified subbase, about 800 TON of Type A granular shoulders, crushed stone driveway surfacing and erosion stone.
  • HaulingTens of thousands of CY of excavation, backfill, embankment and subbase plus about 63,000 SY of pavement removal.
  • GeosyntheticsAbout 78,000 SY of polymer grid subgrade stabilization and 109 SY of engineering fabric.
  • Traffic control27 safety closures, 200 flaggers, 100 pilot cars, temporary traffic signals and 325 LF of temporary concrete barrier rail.
  • Electrical22 lighting poles, about 8,600 LF of electrical circuits, 19 handholes and 2 control cabinets.
  • Signing and pavement markingAbout 600 SF of Type A and about 430 SF of Type B signs, about 1,500 STA of painted markings and preformed thermoplastic markings in cut grooves.
  • Erosion control345 SQ of turf reinforcement mat, about 15,000 LF of sediment control devices, silt fence and seeding.
  • Ready-mix concreteAbout 1,200 SY of 9.5 in. PCC driveways and 43 CY of flowable mortar.
  • Guardrail325 LF of steel beam guardrail with 4 barrier transitions and 4 tangent end terminals.
  • Precast and pipe264 LF of unclassified roadway pipe from 18 to 30 in. and corrugated metal pipe and aprons.

Timing

complete by Nov 22, 2028. Stage 2B complete by November 24, 2027 so traffic runs in the Stage 3 configuration over winter 2027/2028. Stage 5 complete by November 22, 2028, excluding seeding. Seeding and vegetation establishment: 15 working days, late start April 9, 2029.

110In the city of Davenport, On W Central Park Avenue, from Lincoln Ave to 275' west ofReconstruction of W Central Park Avenue in Davenport with about 22,000 SY of PCC pavement, new subdrain, storm and sanitary sewer work, sidewalks and traffic signals.Scott · District 6 (Cedar Rapids)ReconstructionLarge71 itemsWorth a look

City of Davenport project let by Iowa DOT, from Lincoln Ave to 275' west of Fairmount St. About 23,000 SY of pavement is removed and replaced with 9-inch and 8-inch PCC over modified subbase, granular subbase, macadam stone base and polymer grid subgrade stabilization. Work also includes about 9,400 LF of subdrain, RCP storm sewer, PVC sanitary sewer, manholes and intakes, PCC sidewalk and driveways, sign replacement and new traffic signalization (a specialty item). Vibration monitoring and a portable dynamic message sign are included.

W Central Park Avenue · Davenport · Scott County · State ID STP-U-1827(708)--70-82

Key items

PCC pavement, Class C, 9 in.about 20,000SY
Removal of pavementabout 23,000SY
Subdrain, perforated plastic pipe, 6 in.about 9,400LF
Excavation, Class 10, roadway and unsuitable materialabout 7,500CY
Modified subbaseabout 4,100CY
Subgrade stabilization material, polymer gridabout 4,500SY

Who should look

  • Concrete paving and cementAbout 20,000 SY of 9-inch and about 2,000 SY of 8-inch PCC pavement.
  • Aggregate and base suppliersAbout 4,100 CY of modified subbase, 1,500 TON of macadam stone base and 1,500 SY of granular subbase.
  • EarthworkAbout 5,200 CY of roadway excavation, 2,200 CY of unsuitable material excavation and special subgrade compaction.
  • HaulingAbout 7,500 CY of excavation and about 23,000 SY of removed pavement to haul.
  • Ready-mix concretePCC sidewalk at 4, 6 and 8 inches (about 1,200 SY) and about 890 SY of 8-inch PCC driveways.
  • Precast and pipeRCP storm sewer from 12 to 30 inches, PVC sanitary sewer, storm and sanitary manholes, intakes and about 9,400 LF of subdrain.
  • ElectricalTraffic signalization and removal of the existing signals, both lump sum.
  • Signing and pavement markingAbout 340 SF of Type A aluminum signs on steel tube posts, plus durable and painted markings in cut grooves.
  • GeosyntheticsAbout 4,500 SY of polymer grid for subgrade stabilization.
  • Traffic control32 safety closures and 30 calendar days of portable dynamic message sign.
  • Erosion controlAbout 8,100 LF of perimeter sediment control device, intake sediment filters and 465 SQ of sod.

Timing

75 working days. Late start date July 19, 2027. Winter free time not allowed.

111In the city of Long Grove, Multi-Use Use Path, On N 1st St, from Pine St N to City LimitsBuild a 6-in PCC multi-use path along N 1st St in Long Grove, from Pine St north to the city limits.Scott · District 6 (Cedar Rapids)TrailSmall35 items

The City of Long Grove is the contracting authority. Work includes about 1,200 SY of PCC trail on granular subbase, about 880 SY of replaced PCC driveways, about 1,100 LF of 15-in HDPE storm sewer with seven drain basins, and grading. Other items relocate mailboxes, adjust a hydrant and valve box, and remove and reinstall baseball field fence; disturbed areas get sod and seeding.

N 1st St · Long Grove · Scott County · State ID TAP-R-4497(603)--8T-82

Key items

Recreational trail, PCC, 6 in.about 1,200SY
Driveway, PCC, 6 in.about 880SY
Storm sewer, HDPE, 15 in.about 1,100LF
Granular subbaseabout 2,400SY
Embankment-in-placeabout 610CY
Drain basin with dome grate7EACH

Who should look

  • Ready-mix concreteAbout 1,200 SY of 6-in PCC trail and about 880 SY of 6-in PCC driveways.
  • Precast and pipeAbout 1,100 LF of 15-in HDPE storm sewer and 7 drain basins with dome grates.
  • Aggregate and base suppliersAbout 2,400 SY of granular subbase and 8 tons of erosion stone.
  • EarthworkAbout 610 CY of embankment, about 460 CY of excavation and about 380 CY of topsoil.
  • Erosion controlAbout 1,500 LF of sediment control devices, ditch checks, sod and urban seeding.
  • Geosynthetics25 SY of polymer grid subgrade stabilization.
  • Guardrail220 LF of baseball field fence removed and reinstalled.
  • Traffic controlSchedule has safety closures and road closure removal beyond the lump sum traffic control.

Timing

20 working days. Late start date October 4, 2027.

112In the City of Maxwell (ADA - District 1)ADA sidewalk replacement along IA 210 in Maxwell, with new PCC sidewalk, curb and gutter, driveways and intakes.Story · District 1 (Ames)Sidewalk and ADAMedium44 items

Work removes about 2,900 SY of sidewalk and rebuilds it in 4, 6 and 8 in. PCC with detectable warnings, plus curb and gutter, driveways, PCC steps, a combined sidewalk and retaining wall, full-depth patches and a short PCC pavement widening. Drainage work adds intakes and 10 LF of 18 in. RCP storm sewer. Concrete work must be done by August 10, 2027 and final grading and seeding by August 30, 2027.

IA 210 · Maxwell · Story County · State ID STPN-210-3(041)--2J-85

Key items

Removal of sidewalkabout 2,900SY
Sidewalk, P.C. concrete, 6 in.about 1,800SY
Sidewalk, P.C. concrete, 4 in.about 1,700SY
Curb and gutter, P.C. concrete (2.0 and 2.5 ft)about 1,500LF
Driveway, P.C. concrete (6 and 8 in.)about 1,000SY
Detectable warnings568SF

Who should look

  • Ready-mix concreteAbout 3,600 SY of PCC sidewalk, about 1,500 LF of curb and gutter, about 1,000 SY of PCC driveways and full-depth patches.
  • Erosion controlAbout 3,700 LF of 9 in. sediment control device, intake filter bags, bonded fiber matrix mulch and urban seeding.
  • Precast and pipeFour intakes (SW-501 tops and an SW-512) and 10 LF of 18 in. RCP storm sewer.

Timing

complete by Aug 30, 2027. Site 01 (all concrete work) completion August 10, 2027. Site 00 (final grading and seeding) completion August 30, 2027.

113In the city of Creston, on New York Ave from Sumner Ave to Adams StRemoval and replacement of New York Ave in Creston with about 8,300 SY of 8-inch PCC pavement, new sidewalk and driveways.Union · District 4 (Atlantic)ReconstructionMedium28 items

City of Creston project let by Iowa DOT, from Sumner Ave to Adams St. About 8,400 SY of pavement is removed and replaced with 8-inch Class C PCC over modified subbase. Sidewalk and driveways are rebuilt in PCC, with two new intakes and a short run of storm sewer. Non-federal aid; predetermined wages do not apply.

New York Ave · Creston · Union County · State ID STBG-SWAP-1710(612)--SG-88

Key items

PCC pavement, Class C, 8 in.about 8,300SY
Removal of pavementabout 8,400SY
Excavation, Class 10, roadway and borrowabout 2,700CY
Sidewalk, P.C. concrete, 5 and 6 in.about 2,400SY
Modified subbaseabout 1,500CY
Driveway, P.C. concrete, 6 in.about 1,300SY

Who should look

  • Concrete paving and cementAbout 8,300 SY of 8-inch PCC street pavement.
  • Ready-mix concreteAbout 2,400 SY of 5 and 6-inch PCC sidewalk and about 1,300 SY of 6-inch PCC driveways.
  • EarthworkAbout 2,700 CY of roadway excavation and 1,500 CY of compaction with moisture and density control.
  • Aggregate and base suppliersAbout 1,500 CY of modified subbase.
  • HaulingAbout 2,700 CY of excavation and about 8,400 SY of removed pavement to haul.
  • Precast and pipeTwo SW-501 intakes and about 91 LF of 15-inch storm sewer.
  • Erosion controlUrban seeding and mulching on about 1.7 acres.
  • Traffic control12 safety closures.

Timing

60 working days. Late start date July 12, 2027. Winter free time not allowed.

114On Ginkgo Ave, from 170th Street N to Wellman; On Ginkgo Avenue, from IA 92 N to past 170th Street intersectionPCC overlay of Ginkgo Ave from IA 92 north to Wellman, about 163,000 SY placed over a pavement interlayer geotextile, with new granular shoulders and rumble strips.Washington · District 5 (Fairfield)ResurfacingLarge33 itemsWorth a look

Washington County project let by Iowa DOT, in two segments: from IA 92 N to past the 170th Street intersection, and from 170th Street N to Wellman. Concrete is bid as furnish only (about 40,000 CY) and placement only (about 163,000 SY), over about 164,000 SY of interlayer geotextile. Shoulders get about 12,000 TON of Type B granular material, and diamond-ground sinusoidal shoulder and centerline rumble strips are cut in the new surface. A short HMA surface follows pavement scarification.

Ginkgo Ave · Washington County · State ID STP-S-TSF-C092(128)--5P-92, STP-S-TSF-C092(134)--5P-92

Key items

PCC overlay, furnish onlyabout 40,000CY
PCC overlay, placement onlyabout 163,000SY
Pavement interlayer geotextileabout 164,000SY
Granular shoulders, Type Babout 12,000TON
Diamond ground sinusoidal rumble strips, shoulder and centerlineabout 1,200STA
Hot mix asphalt surface course, 1/2 in. mixabout 260TON

Who should look

  • Concrete paving and cementAbout 40,000 CY of PCC overlay concrete furnished and about 163,000 SY placed.
  • GeosyntheticsAbout 164,000 SY of pavement interlayer geotextile under the overlay.
  • Aggregate and base suppliersAbout 12,000 TON of Type B granular shoulders and about 500 TON of special backfill.
  • HaulingAbout 40,000 CY of overlay concrete and 12,000 TON of shoulder stone to deliver.
  • Signing and pavement markingAbout 1,100 STA of painted markings set in about 920 STA of cut grooves.
  • Asphalt / HMAAbout 260 TON of HMA surface course with PG 58-28S binder.

Timing

70 working days. Late start date June 14, 2027. Winter free time not allowed.

116SB Weigh Station 3.2 mi N of Co Rd A38PCC pavement replacement at the I-35 southbound weigh station, with polymer grid subgrade, modified subbase, concrete shoulders and subdrains.Worth · District 2 (Mason City)ReconstructionMedium34 items

The site is the southbound I-35 weigh station 3.2 mi N of Co Rd A38. Work removes about 9,100 SY of pavement and places about 7,881 SY of 10 in. Class C PCC pavement and about 2,899 SY of 10 in. PCC paved shoulder over polymer grid subgrade stabilization and modified subbase, with longitudinal subdrains. It also includes concrete barrier, entrance bollards, a permanent crash cushion, a loop detector and grooved painted markings. Work may not begin before June 1, 2027.

I-35 · Worth County · State ID IMN-035-8(052)212--0E-98

Key items

PCC pavement, Class C, Class 3 durability, 10 in.7,881SY
Subgrade stabilization material, polymer gridabout 12,000SY
Modified subbaseabout 4,100CY
Excavation, Class 13, wasteabout 5,200CY
Paved shoulder, PCC, 10 in.2,899SY
Subdrain, longitudinal (shoulder), 4 in.about 3,200LF

Who should look

  • Concrete paving and cement7,881 SY of 10 in. slip form PCC pavement and 2,899 SY of 10 in. PCC paved shoulder.
  • Aggregate and base suppliersAbout 4,100 CY of modified subbase.
  • GeosyntheticsAbout 12,000 SY of polymer grid subgrade stabilization.
  • EarthworkAbout 5,200 CY of Class 13 waste excavation, about 1,500 CY of topsoil and clearing and grubbing.
  • HaulingAbout 5,200 CY of waste excavation out and about 4,100 CY of modified subbase in.
  • Precast and pipeAbout 3,200 LF of 4 in. longitudinal shoulder subdrain and 23 subdrain outlets.
  • Erosion control4,390 LF of slope sediment control device and a stabilized construction entrance.
  • Signing and pavement markingAbout 64 STA of painted markings in cut grooves.
  • Traffic control20 calendar days of portable dynamic message signs and 2 safety closures.
  • Guardrail49 LF of BA-102 concrete barrier, a BA-105 barrier end and a permanent severe use crash cushion.
  • Ready-mix concreteConcrete barrier and footing and a small PCC sidewalk.
  • Electrical1 loop detector added to an existing traffic signal system.

Timing

45 working days. Late start date August 23, 2027. Work may not begin before June 1, 2027.

151On Dunkerton Road (C66), from Wagner Road (V25) W 0.2 milesRemove and rebuild 0.2 mile of Dunkerton Road (C66) west of Wagner Road (V25) with polymer grid, modified subbase and HMA.Black Hawk · District 2 (Mason City)ReconstructionSmall18 items

Black Hawk County grade and replace project. Removes about 2,600 SY of pavement, excavates about 690 CY of waste, stabilizes the subgrade with about 3,200 SY of polymer grid and builds back with about 540 CY of modified subbase and about 1,350 TON of HMA in three courses. Includes granular shoulders, two HMA rumble strip panels and painted markings.

C66 · Black Hawk County · State ID FM-C007(183)--55-07

Key items

Hot mix asphalt, base, intermediate and surface courses1,350TON
Subgrade stabilization material, polymer gridabout 3,200SY
Removal of pavementabout 2,600SY
Modified subbaseabout 540CY
Excavation, Class 13, wasteabout 690CY
Granular shoulders, Type B350TON

Who should look

  • Asphalt / HMA1,350 TON of standard traffic HMA (850 base, 250 intermediate, 250 surface) and 81 TON of PG 58-28S binder.
  • Aggregate and base suppliersAbout 540 CY of modified subbase and 350 TON of Type B granular shoulders.
  • GeosyntheticsAbout 3,200 SY of polymer grid for subgrade stabilization.
  • HaulingAbout 690 CY of waste excavation out, plus about 1,350 TON of HMA and the subbase and shoulder stone in.
  • EarthworkAbout 690 CY of Class 13 waste excavation.
  • Signing and pavement markingAbout 21 STA of painted pavement markings.
  • Traffic controlSchedule has safety closures beyond the lump sum traffic control.

Timing

15 working days. Late start date September 27, 2027.

152On D20, from Hwy 281 East 5 Miles to Buchanan County LineScarifies and resurfaces about 5 miles of county road D20 with two lifts of hot mix asphalt, from Hwy 281 east to the Buchanan County line.Black Hawk · District 2 (Mason City)ResurfacingMedium15 items

Black Hawk County is the contracting authority for this farm-to-market project. Work scarifies about 66,000 SY of pavement for cross slope and places about 6,100 TON of intermediate and about 6,000 TON of surface course HMA, then rebuilds granular shoulders and paints new markings. Traffic is handled with flaggers.

D20 · Black Hawk County · State ID FM-C007(184)--55-07

Key items

HMA standard traffic, intermediate course, 1/2 in. mixabout 6,100TON
HMA standard traffic, surface course, 1/2 in. mixabout 6,000TON
Asphalt binder, PG 58-28Sabout 720TON
Pavement scarification, cross slopeabout 66,000SY
Granular shoulders, Type Babout 470TON
Painted pavement markingsabout 480STA

Who should look

  • Asphalt / HMAAbout 12,000 TON of 1/2 in. HMA in two courses with about 720 TON of PG 58-28S binder.
  • HaulingAbout 12,000 TON of HMA and about 620 TON of shoulder and driveway stone over a 5-mile route.
  • Aggregate and base suppliersAbout 470 TON of Type B granular shoulders and 150 TON of Class A crushed stone driveway surfacing.
  • Signing and pavement markingAbout 480 STA of painted pavement markings.
  • Traffic controlSchedule has flaggers beyond the lump sum traffic control.

Timing

15 working days. Late start September 27, 2027. Winter free time not permitted.

153On N-28, from Iowa Hwy 83 N 6.7 miles to EOP near I-80 north rampCold in-place recycle 6.7 miles of N28 from IA 83 north to the end of pavement near the I-80 north ramp, then resurface with HMA.Cass · District 4 (Atlantic)ResurfacingMedium16 items

Cass County is the contracting authority. About 78,000 SY of existing pavement is recycled in place with foamed asphalt, then covered with HMA intermediate and surface courses of about 7,000 tons each. Work also includes about 7,000 tons of Type B granular shoulders, pavement scarification, HMA rumble strip panels and painted markings. Traffic is handled with flaggers and pilot cars.

N28 · Cass County · State ID FM-C015(91)--55-15

Key items

Cold in-place recycled asphalt pavementabout 78,000SY
HMA standard traffic, intermediate course, 1/2 in.7,200TON
HMA standard traffic, surface course, 1/2 in.7,000TON
Granular shoulders, Type B7,000TON
Asphalt binder, PG 58-28S850TON
Asphalt stabilizing agent (foamed asphalt)about 310TON

Who should look

  • Asphalt / HMAAbout 14,000 tons of HMA intermediate and surface course, 850 tons of binder and about 78,000 SY of cold in-place recycling with foamed asphalt.
  • Aggregate and base suppliers7,000 tons of Type B granular shoulders.
  • HaulingAbout 14,000 tons of HMA and 7,000 tons of shoulder rock over 6.7 miles.
  • Traffic control50 flaggers and 10 pilot cars.
  • Signing and pavement markingAbout 210 STA of painted pavement markings.

Timing

45 working days. Late start date August 16, 2027.

154Appanoose Co Line to West GroveHMA resurfacing of IA 2 from the Appanoose County line to West Grove, with pavement scarification, HMA base widening, granular shoulders and rumble strips.Davis · District 5 (Fairfield)ResurfacingMedium23 items

The proposal covers about 6.24 miles of IA 2 (cleaning and preparation of base is billed at 6.24 MILE). Work scarifies about 88,000 SY of pavement, widens the base with about 26,000 SY of 5 in. HMA, and places about 7,600 TON of HMA intermediate course and about 7,600 TON of HMA surface course (Friction L-4). It also includes full-depth patches, about 2,900 TON of Type B granular shoulders, milled shoulder and centerline rumble strips and grooved painted markings.

IA 2 · Davis County · State ID NHSX-002-8(038)--3H-26

Key items

Pavement scarification, nominal thicknessabout 88,000SY
Base widening, 5 in. HMAabout 26,000SY
HMA standard traffic, intermediate course, 1/2 in.about 7,600TON
HMA standard traffic, surface course, 1/2 in., Friction L-4about 7,600TON
Excavation, Class 13, for wideningabout 3,600CY
Granular shoulders, Type Babout 2,900TON

Who should look

  • Asphalt / HMAAbout 15,000 TON of HMA intermediate and surface course, about 26,000 SY of 5 in. HMA base widening and about 919 TON of PG 58-28S binder.
  • HaulingAbout 15,000 TON of HMA mix, about 2,900 TON of granular shoulder stone and about 3,600 CY of widening excavation.
  • Aggregate and base suppliersAbout 2,900 TON of Type B granular shoulders and 39 TON of Class A crushed stone surfacing.
  • EarthworkAbout 3,600 CY of Class 13 excavation for widening.
  • Signing and pavement markingAbout 7,900 STA of painted pavement markings and about 1,056 STA of grooves cut for markings.
  • Ready-mix concreteAbout 242 SY of full-depth patches and 25 SY of 8 in. PCC driveway.

Timing

65 working days. Late start date August 2, 2027.

155On K16, from IA 9 N 3 miles to MN State LnCold in-place recycle K16 from IA 9 north 3 miles to the Minnesota state line and cap it with a hot mix asphalt surface course.Lyon · District 3 (Sioux City)ResurfacingMedium25 items

The existing pavement is recycled in place with foamed asphalt stabilizing agent, then surfaced with a 1/2 in. friction L-4 HMA surface course. Shoulders get Type B granular material and milled shoulder and centerline rumble strips. Traffic is handled with flaggers, pilot cars and safety closures. Lyon County is the contracting authority.

K16 · Lyon County · State ID STP-S-C060(127)--5E-60

Key items

Cold in-place recycled asphalt pavementabout 41,000SY
HMA surface course, 1/2 in. mix, friction L-4about 6,200TON
Asphalt binder, PG 58-28Habout 370TON
Asphalt stabilizing agent (foamed asphalt)182TON
Granular shoulders, Type Babout 2,900TON
Excavation, Class 10, roadway and borrowabout 1,700CY

Who should look

  • Asphalt / HMAAbout 6,200 TON of HMA surface course and about 370 TON of binder over about 41,000 SY of cold in-place recycling.
  • Aggregate and base suppliersAbout 2,900 TON of Type B granular shoulders and 40 TON of Class A crushed stone driveway surfacing.
  • HaulingAbout 6,200 TON of HMA, about 2,900 TON of shoulder material and about 1,700 CY of excavation.
  • EarthworkAbout 1,700 CY of Class 10 roadway and borrow excavation.
  • Signing and pavement marking346 STA of painted markings plus 346 STA of temporary painted markings.
  • Traffic control11 safety closures, with 50 flagger days and 18 pilot car days.

Timing

40 working days. Late start date August 30, 2027. Winter work required.

156Melbourne to US 30 (SB)Cold in-place recycles and overlays southbound IA 330 from Melbourne to US 30 with two courses of high traffic HMA, plus new shoulder subdrain and rumble strips.Marshall · District 1 (Ames)ResurfacingLarge27 items

Work recycles about 80,000 SY of existing asphalt in place with foamed asphalt, then places about 9,500 TON each of intermediate and surface course high traffic HMA. It adds about 69,000 LF of 4 in. tile subdrain with about 300 outlets, rebuilds granular shoulders and mills shoulder rumble strips. Full-depth patches, grooved painted markings and portable message signs are included.

IA 330 · Marshall County · State ID NHSX-330-2(102)--3H-64

Key items

Cold in-place recycled asphalt pavementabout 80,000SY
HMA high traffic, intermediate course, 1/2 in. mixabout 9,500TON
HMA high traffic, surface course, 1/2 in. mix, friction L-2about 9,500TON
Subdrain, tile, 4 in. dia.about 69,000LF
Granular shoulders, Type Babout 4,200TON
Milled shoulder rumble strips, HMA surfaceabout 600STA

Who should look

  • Asphalt / HMAAbout 19,000 TON of high traffic 1/2 in. HMA, about 1,100 TON of PG 58-28H binder, and about 260 TON of foamed asphalt for the recycling.
  • HaulingAbout 19,000 TON of HMA and about 4,200 TON of granular shoulder stone.
  • Aggregate and base suppliersAbout 4,200 TON of Type B granular shoulders.
  • Precast and pipeAbout 69,000 LF of 4 in. tile subdrain with about 300 DR-306 outlets.
  • Signing and pavement markingAbout 2,100 STA of painted pavement markings with about 720 STA of grooves cut for markings.
  • Traffic control20 calendar days of portable dynamic message signs.

Timing

70 working days. Late start June 7, 2027. Winter free time not permitted.

157In Cylinder (ADA - District 3); Emmetsburg to Cylinder; 4th St in Cylinder to 0.14 mile E of ECL Cylinder; 0.14 mile E of ECL Cylinder to W Jct IA 15HMA resurfacing with milling, patching and widening on US 18 from Emmetsburg through Cylinder to the west junction of IA 15, plus sidewalk and ADA work in Cylinder.Palo Alto · District 3 (Sioux City)ResurfacingLarge174 items

Three resurfacing projects cover US 18 from Emmetsburg to Cylinder, through Cylinder, and from east of Cylinder to the west junction of IA 15. Work includes pavement scarification, about 4,100 SY of full-depth patches, excavation for widening, a 3/4 in. HMA base course and a 3/8 in. thin lift HMA surface course, granular shoulders, milled shoulder and centerline rumble strips and new guardrail. A fourth project in Cylinder replaces sidewalk with detectable warnings, curb and gutter and driveways. Traffic is handled with flaggers, pilot cars and flaggers with AFAD. Railroad right-of-way and historic structure vibration monitoring provisions apply.

US 18 · Palo Alto County · State ID NHSN-018-3(120)--2R-74, NHSX-018-3(122)--3H-74, NHSN-018-3(123)--2R-74, NHSX-018-3(124)--3H-74

Key items

Pavement scarification (nominal thickness and cross slope)about 200,000SY
Hot mix asphalt thin lift surface course, 3/8 in. mixabout 20,000TON
Hot mix asphalt standard traffic base course, 3/4 in. mixabout 18,000TON
Excavation, Class 13, for wideningabout 10,000CY
Granular shoulders, Type Babout 6,600TON
Patches, full-depth repairabout 4,100SY

Who should look

  • Asphalt / HMAAbout 40,000 TON of HMA, mostly 3/8 in. thin lift surface and 3/4 in. base course, with about 3,200 TON of asphalt binder.
  • Aggregate and base suppliersAbout 6,600 TON of Type B granular shoulders and about 1,600 CY of modified subbase.
  • HaulingAbout 40,000 TON of HMA, about 6,600 TON of granular shoulders and about 12,000 CY of excavation.
  • EarthworkAbout 10,000 CY of Class 13 excavation for widening, about 2,600 CY of waste excavation and about 460 CY of embankment.
  • Traffic control45 flaggers, 60 pilot cars, 75 flaggers with AFAD and 6 safety closures.
  • Ready-mix concreteAbout 930 SY of PCC sidewalk, about 1,000 LF of curb and gutter, PCC driveways, about 600 SY of 8 in. PCC paved shoulder and full-depth PCC patches.
  • Signing and pavement markingAbout 6,700 STA of painted markings in about 1,800 STA of cut grooves, preformed thermoplastic symbols and tape, and 288 SF of Type A signs.
  • Guardrail350 LF of steel beam guardrail with 4 transitions and 4 tangent end terminals, replacing 240 LF.
  • Erosion controlAbout 1,700 LF of perimeter and slope sediment control device, intake filter bags, urban seeding and bonded fiber matrix mulch.

Timing

140 working days. Late start date April 5, 2027.

158Missouri State Line to IA 2Mill, widen and resurface US 169 from the Missouri state line to IA 2 with an HMA intermediate course and a high performance thin lift surface.Ringgold · District 4 (Atlantic)ResurfacingLarge50 itemsWorth a look

Pavement is scarified, patched full depth and widened with 4 in. and 7 in. HMA base widening, then overlaid with a 1/2 in. HMA intermediate course and a 3/8 in. thin lift surface course with polymer modified binder. Shoulders get Type B granular material, contractor stockpiled shoulder material and milled rumble strips with fog seal. The job also replaces four lighting poles with new circuits and a control cabinet, and removes and reinstalls pipe culverts and aprons. Traffic is handled with flaggers, pilot cars and portable message signs.

US 169 · Ringgold County · State ID NHSX-169-1(048)--3H-80

Key items

HMA thin lift surface course, 3/8 in. mixabout 23,000TON
HMA intermediate course, 1/2 in. mixabout 26,000TON
Pavement scarificationabout 219,000SY
Base widening, 4 in. HMA mixtureabout 66,000SY
Granular shoulders, Type B15,800TON
Patches, full-depth repairabout 2,700SY

Who should look

  • Asphalt / HMAAbout 49,000 TON of HMA intermediate and thin lift surface course, about 3,400 TON of binder and about 66,000 SY of HMA base widening.
  • Aggregate and base suppliers15,800 TON of Type B granular shoulders, 2,500 TON of contractor stockpiled shoulder material and 319 TON of Class E revetment.
  • HaulingAbout 49,000 TON of HMA, over 18,000 TON of shoulder material and about 7,700 CY of widening excavation.
  • EarthworkAbout 7,700 CY of Class 13 excavation for widening and ditch reshaping.
  • ElectricalFour lighting poles, 1,100 LF of electrical circuits, handholes and a control cabinet, with removal of old poles and circuits.
  • Signing and pavement markingAbout 11,000 STA of painted markings and about 1,600 STA of grooves cut for markings.
  • Traffic control21 calendar days of portable dynamic message signs, with 330 flagger days and 165 pilot car days.
  • Erosion control600 LF of perimeter sediment control devices, mulching and seeding.

Timing

130 working days. Late start date April 5, 2027. Winter work required.

159In Davenport, from Lombard St to 59th St (NB)HMA resurfacing of northbound IA 461 in Davenport from Lombard St to 59th St, with scarification, full-depth patches and an HMA interlayer.Scott · District 6 (Cedar Rapids)ResurfacingMedium48 items

Iowa DOT scarifies about 89,000 SY of pavement, makes about 1,500 SY of full-depth patches with PCC patch finishing, then places an HMA interlayer base course, leveling course and a high traffic surface course over 2.68 miles. Work also replaces about 390 SY of PCC sidewalk with detectable warnings, adjusts 39 manholes and replaces 7 traffic signal loop detectors. Traffic is handled with flaggers and portable message signs.

IA 461 · Davenport · Scott County · State ID NHSN-461-1(022)--2R-82

Key items

Pavement scarification, nominal thicknessabout 89,000SY
HMA high traffic surface course, 1/2 in. mix, friction L-2about 8,700TON
HMA interlayer base course, 3/8 in. mixabout 5,400TON
HMA wedge, leveling or strengthening courseabout 700TON
Patches, full-depth repairabout 1,500SY
Sidewalk, P.C. concrete, 6 in.about 390SY

Who should look

  • Asphalt / HMAAbout 8,700 TON of high traffic surface course, about 5,400 TON of interlayer base course and about 700 TON of leveling course, with PG 58-28H and 58-34E binder.
  • HaulingAbout 14,000 TON of HMA mixture.
  • Ready-mix concreteAbout 170 SY of full-depth PCC patch finish with joint assemblies and about 390 SY of 6 in. PCC sidewalk.
  • Signing and pavement markingAbout 870 STA of painted markings and preformed thermoplastic markings and symbols in cut grooves.
  • Traffic control100 flaggers and 100 calendar days of portable dynamic message sign.
  • Electrical7 loop detectors added to or replaced in an existing traffic signal system.
  • Erosion control620 LF of curb intake sediment filters, grate intake filter bags and 1,080 LF of slope sediment control device.

Timing

55 working days. Late start date July 12, 2027. Winter free time (Nov 15 to Apr 1) is not allowed.

160Approx 1.1 mi N of US 63 to 0.4 mi S of IA 23Hot in-place recycling and HMA resurfacing of IA 149 from about 1.1 miles north of US 63 to 0.4 miles south of IA 23, with HMA base widening and shoulder subdrain.Wapello · District 5 (Fairfield)ResurfacingLarge56 items

Work hot in-place recycles about 58,000 SY of asphalt pavement with a rejuvenating agent, scarifies the surface, and places about 1,200 TON of HMA intermediate and about 8,800 TON of HMA surface course. It widens the base with HMA, adds about 24,000 LF of longitudinal shoulder subdrain, granular shoulders and a 24 in. concrete roadway pipe culvert, and mills shoulder and centerline rumble strips. Traffic is controlled with pilot cars, flaggers with AFADs, four temporary traffic signals and portable message signs. Winter work is required: the November 15 to April 1 free time does not apply.

IA 149 · Wapello County · State ID STP-149-1(100)--2C-90

Key items

Hot in-place recycled asphalt pavementabout 58,000SY
HMA high traffic, surface course, 1/2 in. mix, Friction L-4about 8,800TON
Base widening, 4.5 in. HMA mixtureabout 16,000SY
Subdrain, longitudinal (shoulder), 4 in. dia.about 24,000LF
Excavation, Class 13, for wideningabout 2,400CY
Granular shoulders, Type Babout 1,500TON

Who should look

  • Asphalt / HMAAbout 10,000 TON of HMA surface and intermediate course, about 600 TON of asphalt binder, HMA base widening and about 58,000 SY of hot in-place recycling.
  • HaulingAbout 10,000 TON of HMA plus excavation and shoulder stone to move.
  • Traffic controlFour temporary traffic signals, 120 calendar days of portable dynamic message signs, pilot cars and flaggers with AFADs.
  • Signing and pavement markingAbout 2,600 STA of painted markings, about 560 STA of grooves cut for markings and preformed thermoplastic tape and symbols.
  • Aggregate and base suppliersAbout 1,500 TON of Type B granular shoulders and Class A crushed stone surfacing.
  • EarthworkAbout 2,400 CY of Class 13 excavation for widening, plus embankment and ditch reshaping.
  • Precast and pipe40 LF of 24 in. concrete roadway pipe culvert with seven aprons, and about 24,000 LF of 4 in. shoulder subdrain with 94 outlets.
  • Erosion controlAbout 3,000 LF of perimeter and slope sediment control devices.

Timing

60 working days. Late start date August 16, 2027. Winter work is required: the November 15 to April 1 free time does not apply.

161On Lenox Ave NE 0.4 miles to D38 and 210th St 0.5 mi W of IA 31; On 220th Street, from East City limits of Anthon E 6 miles to Safford Avenue; On L 27, from D 50 S 6 miles to D 54Cold in-place recycling and HMA resurfacing on about 12 miles of D38 and L27, plus HMA resurfacing on Lenox Ave and 210th St.Woodbury · District 3 (Sioux City)ResurfacingLarge67 itemsWorth a look

Woodbury County project in three parts: D38 (220th Street) from the east city limits of Anthon east 6 miles to Safford Avenue, L27 from D50 south 6 miles to D54, and Lenox Ave and 210th St near IA 31. D38 and L27 get about 150,000 SY of cold in-place recycled asphalt with foamed asphalt, then about 30,000 TON of HMA in two courses and new granular shoulders. With Lenox Ave and 210th St, the contract has about 32,000 TON of HMA. The D38 section also has sidewalk with detectable warnings, intakes, HDPE storm sewer, a lighting pole and guardrail end work. Traffic runs under flaggers and pilot cars.

D38, L27, Lenox Ave · Woodbury County · State ID L-160--73-97, FM-C097(156)--55-97, FM-C097(157)--55-97

Key items

Cold in-place recycled asphalt pavementabout 150,000SY
Hot mix asphalt, intermediate and surface coursesabout 32,000TON
Pavement scarificationabout 91,000SY
Granular shoulders, Type Babout 8,300TON
Asphalt binder, PG 58-34Sabout 1,900TON
Asphalt stabilizing agent (foamed asphalt)about 570TON

Who should look

  • Asphalt / HMAAbout 32,000 TON of standard traffic HMA, about 1,900 TON of PG 58-34S binder, about 150,000 SY of cold in-place recycling and about 570 TON of foamed asphalt.
  • HaulingAbout 32,000 TON of HMA and about 8,300 TON of shoulder stone across three county roads.
  • Aggregate and base suppliersAbout 8,300 TON of Type B granular shoulders across the three sections.
  • Traffic control70 flaggers, 35 pilot cars and 49 safety closures.
  • Signing and pavement markingAbout 1,200 STA of painted pavement markings.
  • GuardrailSteel beam guardrail removal, four BA-221 barrier transitions, end anchors and BA-225 end terminals on D38.
  • Ready-mix concrete236 SY of 4 in. and 6 in. PCC sidewalk with 150 SF of detectable warnings on D38.
  • Precast and pipe68 LF of 12 in. HDPE storm sewer, 29 LF of 6 in. HDPE and three modified SW-511 and SW-513 intakes.
  • ElectricalOne lighting pole and removal of a light pole foundation.
  • EarthworkAbout 580 CY of roadway and borrow excavation on D38 and L27.

Timing

90 working days. Late start date June 14, 2027.

201WCL of Centerville to IA 5Full-depth PCC patching on IA 2 from the west corporate limits of Centerville to IA 5.Appanoose · District 5 (Fairfield)Pavement maintenanceSmall9 items

Work places about 760 SY of full-depth finished PCC patches, most 50 ft or longer, with CD joint assemblies and CT joints. Traffic is handled with flaggers and pilot cars. Winter work is required: the November 15 to April 1 free time does not apply.

IA 2 · Appanoose County · State ID MP-002-5(709)170--76-04

Key items

Patches, full-depth finish, by area (50 ft or greater in length)about 680SY
Patches, full-depth finish, by areaabout 70SY
Patches, full-depth finish, by count5EACH
CD joint assembly7EACH
CT joint7EACH

Who should look

  • Ready-mix concreteAbout 760 SY of full-depth PCC patches.
  • Traffic controlSchedule has flaggers and pilot cars beyond the lump sum traffic control.

Timing

15 working days. Late start date October 25, 2027. Winter work is required: the November 15 to April 1 free time does not apply.

2021.68 mi E of Co Rd N20 to Burgess Ave in Carroll; 0.54 mi E of Olympic Ave in Carroll to Colorado St in GliddenFull-depth PCC patching on two stretches of US 30 near Carroll and Glidden, with crack cleaning and filling on one of them.Carroll · District 3 (Sioux City)Pavement maintenanceSmall16 items

Site one runs 1.68 mi E of Co Rd N20 to Burgess Ave in Carroll and gets about 1,430 SY of full-depth patches by area, 144 patches by count and 12 CD joint assemblies. Site two runs 0.54 mi E of Olympic Ave in Carroll to Colorado St in Glidden and gets about 362 SY of patches, 35 patches by count and 4.5 miles each of pavement and shoulder crack cleaning and filling. Site two is worked under flaggers, pilot cars and flaggers with AFAD.

US 30 · Carroll County · State ID MP-030-3(719)80--76-14, MP-030-3(720)85--76-14

Key items

Patches, full-depth finish, by area (both sites)about 1,790SY
Patches, full-depth finish, by count (both sites)179EACH
Cleaning and filling cracks (pavement and shoulder)4.5 eachMILE
Filler material (maintenance)2,250GAL
CD joint assembly12EACH

Who should look

  • Ready-mix concreteAbout 1,790 SY of full-depth PCC patches plus 179 patches by count across the two sites.
  • Traffic control30 flaggers, 15 pilot cars and 30 flaggers with AFAD on the Glidden site.

Timing

35 working days. Late start date September 6, 2027.

203E Jct IA 9 to Minnesota State LineFull-depth PCC patching on US 169 from the east junction of IA 9 to the Minnesota state line.Kossuth · District 2 (Mason City)Pavement maintenanceSmall8 items

Work places about 1,900 SY of full-depth PCC patches plus 143 patches by count, with bond breaker. Traffic is controlled with flaggers, pilot cars and flaggers with automated flagger assistance devices.

US 169 · Kossuth County · State ID NHSN-169-8(073)--2R-55

Key items

Patches, full-depth finish, by areaabout 1,900SY
Patches, full-depth finish, by count143EACH
Bond breaker for PCC patchesabout 170SY
Flagger with AFAD40EACH

Who should look

  • Ready-mix concreteAbout 1,900 SY of full-depth PCC patches plus 143 patches by count.
  • Traffic control40 flagger with AFAD units and 20 pilot cars.

Timing

25 working days. Late start September 27, 2027. Winter free time not permitted.

2041 mi N of the Des Moines River to 0.5 mi S of Co Rd W62/Argyle Rd (NB)Full-depth PCC patching, cross-stitched tie bars and crack and joint sealing on northbound IA 27 north of the Des Moines River.Lee · District 5 (Fairfield)Pavement maintenanceSmall11 items

Work runs on northbound IA 27 from 1 mi north of the Des Moines River to 0.5 mi south of Co Rd W62/Argyle Rd. It covers about 87 SY of full-depth PCC patches plus 7 patches by count, 1,336 cross-stitched tie bars and 2 miles of crack and joint cleaning and filling with PCC sealer. Traffic is handled with flaggers and pilot cars. Winter free time is not allowed on this contract.

IA 27 · Lee County · State ID MP-027-5(709)1--76-56

Key items

Cross-stitched tie bar1,336EACH
Patches, full-depth finish, by areaabout 87SY
Patches, full-depth finish, by count7EACH
Crack and joint cleaning and filling (PCC pavement)2MILE
Flaggers20EACH
Pilot cars10EACH

Who should look

  • Ready-mix concreteAbout 87 SY of full-depth PCC patches plus 7 patches by count, with CD and CT joints.
  • Traffic control20 flaggers and 10 pilot cars.
  • Rebar and structural steel1,336 cross-stitched tie bars.

Timing

15 working days. Late start date October 18, 2027. Winter free time (Nov 15 to Apr 1) not permitted.

206In Columbus Junction, from IA 92 north 1.5 milesFull-depth concrete patching on IA 70 in Columbus Junction, from IA 92 north 1.5 miles.Louisa · District 5 (Fairfield)Pavement maintenanceSmall8 items

Crews place about 370 SY of full-depth concrete patches at 20 locations, with CD joint assemblies and CT joints. Traffic is handled with flaggers and pilot cars.

IA 70 · Columbus Junction · Louisa County · State ID MP-070-5(706)1--76-58

Key items

Patches, full-depth finish, by areaabout 370SY
Patches, full-depth finish, by count20EACH
CD joint assembly18EACH
CT joint8EACH

Who should look

  • Ready-mix concreteAbout 370 SY of full-depth concrete patching.
  • Traffic controlSchedule has flaggers and pilot cars beyond the lump sum traffic control.

Timing

15 working days. Late start date October 18, 2027. Winter work required.

207NCL Akron to 8th St in HawardenMicro mill and scrub seal IA 12 from the north city limits of Akron to 8th St in Hawarden.Plymouth · District 3 (Sioux City)ResurfacingMedium25 items

About 162,000 SY of pavement is micro milled and then scrub sealed with polymer modified emulsion and cover aggregate. Work adds milled sinusoidal centerline rumble strips with a penetrating engineered fog seal, painted markings in cut grooves, preformed thermoplastic symbols, steel beam guardrail replacement, a short PCC paved shoulder and full-depth patches.

IA 12 · Plymouth County · State ID STPN-012-2(052)--2J-75

Key items

Scrub seal areaabout 162,000SY
Micro millingabout 162,000SY
Emulsion for scrub sealabout 56,000GAL
Painted pavement markings, waterborne or solvent-basedabout 4,500STA
Penetrating engineered emulsion for fog seal (centerline rumble strips)about 7,800SY
Milled centerline sinusoidal rumble strips, HMA surfaceabout 600STA

Who should look

  • Aggregate and base suppliersThe scrub seal over about 162,000 SY takes cover aggregate under special provision SP-230455.
  • Signing and pavement markingAbout 4,500 STA of painted markings, about 1,500 STA of grooves cut for markings and preformed thermoplastic symbols.
  • Guardrail390 LF of guardrail removed and 150 LF of steel beam guardrail placed with transitions and end terminals.
  • Ready-mix concreteAbout 190 SY of 8 in. PCC paved shoulder and about 45 SY of full-depth patches.
  • EarthworkAbout 270 CY of contractor furnished embankment and 60 TON of special backfill.
  • Traffic controlSchedule has safety closures beyond the lump sum traffic control.

Timing

50 working days. Late start date July 26, 2027. Winter work required.

208Division St in Hull to College Dr. in SheldonMicro milling and microsurfacing on about 13.6 miles of US 18 from Hull to Sheldon, with full-depth patching, guardrail and new grooved markings.Sioux · District 3 (Sioux City)ResurfacingLarge33 items

Iowa DOT project on US 18 from Division St in Hull to College Dr. in Sheldon. About 190,000 SY is micro milled, then microsurfaced with friction L-2 aggregate and emulsified asphalt, with a fog seal on the shoulders. Other work includes full-depth patches, a short 8-inch PCC paved shoulder, about 700 LF of new steel beam guardrail, milled centerline rumble strips and markings in cut grooves. Traffic is carried with flaggers, pilot cars and automated flagger assistance devices.

US 18 · Sioux County · State ID NHSN-018-1(101)--2R-84

Key items

Micro millingabout 190,000SY
Emulsified asphalt for microsurfacingabout 55,000GAL
Aggregate for microsurfacing, friction L-2about 1,900TON
Painted pavement markingsabout 5,300STA
Steel beam guardrailabout 700LF
Patches, full-depth finish, by areaabout 430SY

Who should look

  • Aggregate and base suppliersAbout 1,900 TON of friction L-2 aggregate for microsurfacing.
  • Asphalt / HMAAbout 55,000 GAL of emulsified asphalt for microsurfacing and about 3,900 GAL of fog seal emulsion.
  • Signing and pavement markingAbout 5,300 STA of painted markings, about 1,400 STA of grooves, and preformed thermoplastic tape and symbols.
  • Traffic control140 flagger days, 50 pilot car days and 90 flagger-with-AFAD days.
  • GuardrailAbout 700 LF of steel beam guardrail with 7 barrier transitions and end terminals, plus a permanent crash cushion.
  • Ready-mix concreteFull-depth patches (about 430 SY) and about 660 SY of 8-inch PCC paved shoulder.
  • EarthworkAbout 410 CY of contractor-furnished embankment and about 200 CY of special backfill.

Timing

60 working days. Late start date July 26, 2027. Winter free time not allowed.

209US 20 to Co Rd C70 in Plymouth CountyFull-depth PCC patching on US 75 from US 20 to county road C70 in Plymouth County.Woodbury / Plymouth · District 3 (Sioux City)Pavement maintenanceSmall9 items

Iowa DOT maintenance project on US 75. About 4,000 SY of full-depth PCC patches by area, including about 540 SY of patches 50 ft or longer with subbase, plus 378 patches by count and joint assemblies.

US 75 · Woodbury / Plymouth County · State ID MP-075-3(710)94--76-97

Key items

Patches, full-depth finish, by areaabout 3,400SY
Patches, full-depth finish, by area (50 ft or greater)about 540SY
Patches, full-depth finish, by count378EACH
Subbase (patches)about 540SY
CD and CT joints35EACH

Who should look

  • Ready-mix concreteAbout 4,000 SY of full-depth PCC patches by area and 378 patches by count.
  • Aggregate and base suppliersAbout 540 SY of subbase under the long patches.

Timing

50 working days. Late start date August 16, 2027.

301I-680 to I-880 - Various LocationsForeslope erosion repair on I-29 at various locations between I-680 and I-880, with excavation, topsoil and seeding.Pottawattamie · District 4 (Atlantic)GradingMedium18 items

Work places about 35,000 SY of major foreslope erosion countermeasure (Detail 570-22) at various locations along I-29, with about 4,700 CY of waste excavation, about 9,100 CY of topsoil furnished and spread, and clearing and grubbing. Roadside items include native grass and salt tolerant seeding, mulching and sediment control. Winter work is required: the November 15 to April 1 free time does not apply.

I-29 · Pottawattamie County · State ID IMX-029-4(148)62--02-78

Key items

Foreslope erosion countermeasure, major (Detail 570-22)about 35,000SY
Topsoil, furnish and spreadabout 9,100CY
Excavation, Class 13, wasteabout 4,700CY
Excavation, Class 13, roadway and borrowabout 640CY
Clearing and grubbing7.3ACRE
Native grass seeding6.6ACRE

Who should look

  • EarthworkAbout 4,700 CY of waste excavation, about 640 CY of roadway and borrow excavation, topsoil and 7.3 acres of clearing and grubbing.
  • HaulingAbout 9,100 CY of topsoil in and about 4,700 CY of waste excavation out.
  • Aggregate and base suppliersAbout 35,000 SY of foreslope erosion countermeasure billed under Section 2507, revetment and erosion stone.
  • Erosion controlNative grass and salt tolerant seeding, about 8 acres of mulching, sediment control devices and a stabilized construction entrance.

Timing

80 working days. Late start date June 28, 2027. Winter work is required: the November 15 to April 1 free time does not apply.

352Various Counties and Routes in District 1Multi-component liquid pavement markings on various routes in Iowa DOT District 1.Boone / Greene / Grundy / Hamilton / Hardin / Jasper / Marshall / Polk / Poweshiek / Story / Tama / Webster · District 1 (Ames)Safety and trafficSmall3 items

Iowa DOT pavement marking contract on various counties and routes in District 1, on the Interstate road system. About 7,000 STA of multi-component liquid markings, with traffic control and mobilization.

MULTIPLE ROUTES · Boone / Greene / Grundy / Hamilton / Hardin / Jasper / Marshall / Polk / Poweshiek / Story / Tama / Webster County · State ID NHSN-000-T(479)--2R-00

Key items

Painted pavement markings, multi-component liquidabout 7,000STA

Who should look

  • Signing and pavement markingAbout 7,000 STA of multi-component liquid pavement markings.

Timing

25 working days. Late start date September 13, 2027.

353W of IA 21 to E of IA 21; W of IA 21 to E of IA 21 (EB/WB)Replace three light poles and install an ITS pole, cabinet and fiber optic run on I-80 at IA 21.Poweshiek · District 1 (Ames)Safety and trafficSmall29 items

Two Iowa DOT projects on I-80 west to east of IA 21. The lighting project removes three light poles and their foundations, installs three new poles, 740 LF of circuits and a control cabinet, and demolishes old circuits. The ITS project installs a pole, power foundation and device cabinet (install only) with about 770 LF of bored HDPE conduit and about 880 LF of 12-strand fiber optic cable.

I-80 · Poweshiek County · State ID IM-080-6(518)202--13-79, ITS-080-6(550)201--25-79

Key items

Lighting poles3EACH
Electrical circuits740LF
ITS conduit, HDPE, 1.25 in., boredabout 770LF
Fiber optic cable, 12 SM dielectricabout 880LF
XHHW copper wire, No. 6 and No. 8 AWGabout 2,000LF
Control cabinet1EACH

Who should look

  • ElectricalThree lighting poles, 740 LF of circuits, a control cabinet, about 770 LF of bored ITS conduit, about 880 LF of fiber optic cable and about 2,000 LF of copper wire.

Timing

35 working days. Late start date September 6, 2027.

354On Various County RoadsPainted pavement markings on various Union County roads.Union · District 4 (Atlantic)Safety and trafficSmall3 items

Union County project on farm to market roads. About 5,100 STA of waterborne or solvent-based painted pavement markings, with traffic control and mobilization.

VARIOUS ROUTES · Union County · State ID FM-C088(72)--55-88

Key items

Painted pavement markings, waterborne or solvent-basedabout 5,100STA

Who should look

  • Signing and pavement markingAbout 5,100 STA of waterborne or solvent-based painted pavement markings.

Timing

15 working days. Late start date October 11, 2027.

401Parcel 8, 28477 564th Ave, AmesSalvage, removal and disposal of obstructions on right-of-way Parcel 8, 28477 564th Ave, Ames, for an I-35 project.Story · District 1 (Ames)OtherSmall1 items

A single lump sum item covers salvage, removal and disposal of obstructions on Parcel No. 8. The proposal does not list what the obstructions are.

I-35 · Story County · State ID IMN-035-4(358)107--0E-85

Key items

Salvage, removal, and disposal of obstructions on Parcel No. 8lump sumLS

Who should look

    Timing

    15 working days. Approximate start February 15, 2027.

    501From Solon to Mount VernonClearing and grubbing along IA 1 from Solon to Mount Vernon, with cut-stump herbicide treatment.Johnson · District 6 (Cedar Rapids)OtherSmall6 items

    Iowa DOT maintenance project. About 1,000 units of clearing and grubbing and about 1,100 cut-stump herbicide applications along IA 1 between Solon and Mount Vernon. Traffic is handled with flaggers and automated flagger assistance devices.

    IA 1 · Johnson County · State ID MP-001-6(726)98--76-52

    Key items

    Clearing and grubbingabout 1,000UNIT
    Herbicide application, cut stumpabout 1,100EACH
    Flaggers10EACH
    Flagger with AFAD10EACH

    Who should look

    • EarthworkAbout 1,000 units of clearing and grubbing (Section 2101).
    • Traffic control10 flagger days and 10 flagger-with-AFAD days.

    Timing

    20 working days. Late start date March 1, 2027. Winter free time not allowed.

    Want only the proposals that fit your business?

    When a letting posts in a state we cover, LeadSifter reads it and emails you the projects that call for your products. Ask for a sample report built for what you sell.

    Letting December 15, 2026, as advertised when LeadSifter first saw it on November 18, 2026. Addenda posted after that date are not reflected. Check the Iowa DOT letting page before you bid.

    Built from the DOT's own proposal PDFs (schedule of items, special provisions). Quantities are rounded down and units are as published. No prices, estimates or bidders are shown. Districts are Iowa DOT's six districts, assigned by county. Titles are the location lines printed in each Iowa DOT proposal. Several proposals are county or city projects let by Iowa DOT. Proposal 205 is not described here. Its documents were not in our system when we read the letting. Proposal 351 is a statewide guide sign replacement contract with no sites named, so it is not on the map. Proposal 352 is a District 1 pavement marking contract and is counted in each District 1 county.